Increased reliability for Southend rail passengers: Easter 2022 OHL renewal Pitsea 3

Wednesday 20 Apr 2022

Increased reliability for Southend rail passengers

Region & Route:
Eastern: Anglia

Network Rail continued work on upgrading the overhead wiring system on the line between London and Shoeburyness over the four-day Easter period, improving reliability for thousands of passengers.

The work is part a project to replace the old wiring system with a new wiring system that withstands the heat, resulting in fewer delays caused by overhead wire issues. The four-year project began at Easter last year (2021).

The overhead wiring system on this line was installed between 1959 and 1962 and is vulnerable to the heat which causes delays during the summer months. When the weather is hot, the overhead wires sag. These sagging wires can get caught on the pantograph of passing trains, bringing the wires down which results in long delays and cancellations.

The new wiring system stays taught in all weathers and is generally a more reliable and sustainable system which will require less maintenance. This means less cost to the taxpayer and fewer delays to passengers using the line now and in the future.

Ellie Burrows, Network Rail’s route director for Anglia, said: “This work is essential to improve reliability on this line for the benefit of passengers, freight customers and communities, for years to come. The Easter period has enabled us to complete a large chunk of this four-year project.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk