Improvement work continues at stations on the Penistone line: Improvement work continues at stations on the Penistone line

Tuesday 24 Dec 2019

Improvement work continues at stations on the Penistone line

Region & Route:
Eastern

Network Rail is working with Northern to extend the platform at Honley station and both platforms at Shepley station in the new year. This will mean longer trains with more seats can call at both places, providing a better experience for passengers on the Penistone line.

Work starts on Saturday, 4 January to lengthen platforms 1 and 2 at Shepley station and is expected to be completed by Wednesday, 26 February. Work to extend the platform at Honley station will begin on Monday, 6 January and is expected to be completed by Tuesday, 31 March.

None of this work will impact on train services, and Network Rail is working closely with Northern to minimise any disruption for passengers and residents who live near the railway. The upgrades are part of a wider project to extend more than 100 platforms at over 70 stations across the North of England.

Matt Rice, Route Director for Network Rail, said: “This work to extend the platforms at Shepley and Honley means passengers will benefit from modern trains with increased capacity.

“We are working closely with Northern as we extend seven stations on the Penistone line. I would like to thank people for their patience, and we will make every effort to minimise the noise whilst this work is carried out.”

Anna Weeks, Regional Director at Northern, said: “The work being carried out by Network Rail will allow us to run better, longer trains for our customers – giving them an improved journey experience.

“We are working with Network Rail to keep disruption to a minimum and I’d like to also give my thanks to our customers for their understanding while the work takes place.”

ENDS

Notes to Editors

Platform extensions are taking place at seven stations on the Penistone line:

  • Brockholes
  • Huddersfield
  • Berry Brow
  • Lockwood
  • Shepley
  • Honley
  • Denby Dale

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Kathryn Muffett
Media Relations Manager
Network Rail
01904 383180
kathryn.muffett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk