Wednesday 3 Jun 2020

Iconic Tay Bridge is having sleepers renewed

Region & Route:
Scotland’s Railway: Scotland

Work is now underway to replace more than 1,200 sleepers located on the Tay Bridge, the longest railway structure in Scotland.

This project, which will be ongoing until September, is designed to extend the life of the track and is being delivered in a way which minimises the disruption for passengers.  It represents an investment of more than £500,000 to improve the resilience and reliability of the line for passengers.

One in three sleepers including base-plates and Pandrol clips - which hold the tracks onto the sleepers - are being replaced and ballast below renewed and re-packed. This will deliver improvements to the stability and extend the lifespan of the track. 

It represents an investment of more than £500,000 to improve the resilience and reliability of the two-mile-long structure and follows on from the £75m restoration of the bridge’s metalwork completed in 2017.

Some of the sleeper’s base plates date back to the early 1960’s and the timber sleepers are now at the end of their natural life having been open to the elements and the impacts of the salty air in this exposed coastal location.

It equates to circa 60 tonnes of sleepers being installed and an equivalent amount of redundant material and spoil being removed from the bridge over the period of the project.

This approach being taken delivers a balance between maintaining the track to ensure it is fit for the volume of traffic travelling over the bridge while avoiding disruption to passenger services on the busy East Coast Mainline.

Grant Ritchie, Network Rail’s works delivery manager delivering the Tay Bridge re-sleepering project said, “We work every night to keep the railway open and running efficiently for key workers and essential journeys. Projects like this will benefit even more passengers when lock-down is lifted and we begin to move towards a new kind of normal.

“Any project on an historic and iconic structure like the Tay Bridge is always a pleasure but it presents its own problems due to its unique design and location.  Being open to the elements over the Firth of Tay is unpredictable in itself even when the work is during the summer months.

“Working in a confined location, such as on a bridge, also presents a logistical challenge in normal times but we now have the additional element of ensuring physical distancing, where possible. To do this we are following best advice, using additional protective equipment and learning new ways of working that will help keep everyone safe and let us get the job done.”

 

Notes to Editors

The Tay Bridge opened in 1887 and spans more than three kilometres in length.  Work will be delivered over 51 shifts between April and September.

60 tonnes of timber sleepers - 1,200 in total - will be replaced on the structure.

Network Rail completed a £75m restoration of the structure in 2017.  The project won best entry at the 2018 National Rail Heritage Awards

This work on the Category A-listed structure included a programme of strengthening, repair, grit-blasting and repainting works - with a total of 245,000 square metres of wrought iron and steel being repainted.

The iconic bridge, which carries the railway across the Firth of Tay, is the longest rail structure in Scotland at 3.26km (2 miles).

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk