Monday 22 Sep 2025
Huddersfield station set to reopen next week with new temporary layout
- Region & Route:
- Eastern
Huddersfield station will reopen on Monday 29 September with three rebuilt and extended platforms under new numbering, marking an important step in the Transpennine Route Upgrade (TRU).
From this date, only platforms 1, 2 and 3 will be in use, meaning trains will run to and from different platforms than before and some services will be replaced by rail replacement buses. Passengers are advised to check the latest information before travelling and allow extra time when using the station.
While the station will be open, phase two of the upgrades will continue behind a sectioned-off area, allowing construction teams to complete the remaining platform, canopy and track work. Once finished in early 2027, Huddersfield station will be able to accommodate longer trains with more seating capacity, delivering more comfortable and reliable journeys.
During this stage of the upgrade, some services* will be affected. Stations including Cottingley, Morley, Batley, Ravensthorpe, Brighouse, Halifax, Low Moor and Bradford Interchange will not have direct trains to Huddersfield, and customers may need to change trains as part of their journey.
Passengers are advised to plan ahead and check the latest travel information at www.nationalrail.co.uk. Extra staff will be on hand at Huddersfield and other key stations to provide advice and assistance.
Paul Sumner, Senior Sponsor for TRU, said: “We're looking forward to reopening Huddersfield station at the end of this month, however, we know customers will notice some changes. This includes trains arriving/departing from different platforms and some temporary service alterations.
"We want to thank customers for their patience as we continue this once-in-a-generation investment and would encourage anyone travelling through the area to plan their journey ahead of time.”
Chris Nutton, Major Projects & TRU Director at TransPennine Express, said: “We’re excited to welcome customers back to Huddersfield station next week and for them to see all the work that has taken place whilst the station was closed.
“As we move into phase two of the Huddersfield station upgrade, it will look and operate differently than it did before – with fewer platforms available and some minor changes to TransPennine Express services.
“With one week to go before the station reopens, we encourage customers to plan ahead and check if these changes will affect you.”
The Transpennine Route Upgrade is a multi-billion-pound programme transforming rail travel across the North, delivering faster journey times, increased capacity and more reliable services between Manchester, Huddersfield, Leeds and York.
Notes to Editors
Changes to train services*
When Huddersfield station reopens on Monday 29 September, it will have three extended platforms instead of six. The platforms will be renumbered:
- Platform 2 (Sheffield services) becomes platform 1
- Platform 1 (Manchester services) becomes platform 2
- Platform 4 (Leeds services) becomes platform 3
These changes will remain until early 2027 when the full station upgrade completes.
Changes to Northern services
Local stopping services from Leeds will now start/terminate at Bradford Interchange (Halifax on Sundays), with additional stops at Low Moor, Halifax and Brighouse. These services will no longer call at Huddersfield and Deighton.
Huddersfield to Bradford Interchange services will not run. Rail replacement buses will operate between Huddersfield and Brighouse via Deighton.
Changes to TransPennine Express (TPE) services
TPE will run normal services with two exceptions:
- Manchester Piccadilly to York services will not call at Deighton
- Manchester to Huddersfield peak services will be extended to run non-stop to Leeds
Deighton station
Deighton station closed temporarily on 30 August for upgrade works and will reopen in 2027. An hourly rail replacement bus runs between Huddersfield and Deighton, and from 29 September will also stop at Brighouse.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Chantele Hodson
Communications Manager
chantele.hodson@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk