Haverfordwest residents invited to find out more about Milford Road bridge replacement: Milford Road Railway Bridge-3

Tuesday 29 Jan 2019

Haverfordwest residents invited to find out more about Milford Road bridge replacement

Region & Route:
Wales & Western: Wales & Borders
| Wales & Western

Haverfordwest residents are invited to a ‘drop-in’ event to find out more about the upcoming replacement of Milford Road railway bridge, which will be delivered in February 2019.

Between Friday 15 and Monday 18 February, Network Rail engineers will demolish the existing railway bridge deck - which carries the South Wales Main Line - and install a new, more resilient structure as part of Network Rail’s Railway Upgrade Plan to improve the reliability of the railway.

For Network Rail teams to safely deliver the work, the A4076 at Milford Road railway bridge on Dredgeman Hill will be closed to traffic, with the exception of residents within the road closure and emergency services, from 7pm on Friday 15 February until 6am on Monday 18 February. A signposted diversion route will be in place, with a shuttle bus service in operation for pedestrians and cyclists needing to pass under Milford Road railway bridge during the closure.

Buses will replace trains between Whitland and Milford Haven on Saturday 16 and Sunday 17 February, and timetables will be amended so rail passengers are urged to check before travelling at nationalrail.co.uk.

A ‘drop-in’ event for residents and local businesses will take place on Thursday, 7 February 3pm to 6pm at the Merlins Bridge Welfare Hall, Pembroke Road, SA61 1JW. No appointment is necessary and representatives from Network Rail’s project team will be on hand to provide information and answer any questions.

Rhys Howells, scheme project manager for Network Rail in Wales and Borders, said: “We understand that closing the roads for any length of time is inconvenient and we thank the local community, road users and rail passengers for bearing with us whilst we complete the essential replacement of Milford Road railway bridge.

“We have been working closely with our partners to minimise disruption, and to develop the diversionary routes. I would encourage anyone wishing to find out more about these essential works to attend the drop-in session, where we will be happy to answer any questions.”

For teams to complete preparatory and finishing works safely and effectively, there will be single lane traffic management system in place overnight at the bridge on Dredgeman Hill on the A4076, intermittently up until Sunday 3 March.

The work forms part of the £4.25m upgrade project to improve the reliability of the railway in West Wales, which saw the successful replacement of Pembroke Road railway bridge earlier this month. For more information visit www.networkrail.co.uk/merlins-bridge

Notes to Editors

*Notes to editors – 

To ensure we can complete the preparatory and finishing work safely and effectively a single lane traffic management system, with three-way traffic lights, will be in operation on the A4076 at Milford Road railway bridge during the following days and times:

From 8pm on Saturday to 10am Sunday on the following dates:

2 February - 3 February

9 February - 10 February

23 February - 24 February

2 March - 3 March

From 7pm to 6am (overnights) on Monday, Tuesday, Wednesday, Thursday and Friday, on the following dates:

28 January - 1 February

4 February- 8 February

19 February- 22 February

25 February - 1 March

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Bryony Parry
Media Relations Manager
07734 649220
Bryony.Parry@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk