Friday 5 Apr 2013
Hatfield & Stainforth update – 5 April 2013
- Region & Route:
The complex job of stabilising the spoil heap at Hatfield colliery which slipped and caused extensive damage to the railway continues. However it is now anticipated this may take until the end of the summer to complete.
Network Rail has been working with experts from the colliery since movement was detected in early February. Initial estimates had indicated the line could be restored as soon as July. However a combination of the difficult conditions and continuing bad weather mean that date is at risk.
Phil Verster, Route Managing Director, explained: “This site is incredibly complex and, if not properly managed, potentially dangerous. We have been actively involved on site for several weeks but the processes required to make the ground safe to work on are slower than we had hoped. I fully appreciate the importance of restoring a direct rail service to communities and businesses in Cleethorpes, Scunthorpe, Goole and other places affected by the slip and my team and I are committed to do so as quickly as possible. We continue to aim for restoration of services in July, however we now anticipate that the railway may not be repaired until September this year.
“We will do anything we can do to safely accelerate the repair programme and to reinstate services. In the meantime we are working with the operators of passenger and freight traffic to make best use of the network during this difficult time. That process continues and if there are changes we can make to improve the service we are able to offer then we will. We remain grateful to the patience of passengers and freight customers as we deal with this issue.”
Several sets of engineering works which had been planned by Network Rail are being revised in order to keep as many services running as possible. In particular the GNGE line project is being adapted in order to allow the 140 freight trains which would normally run through Hatfield & Stainforth each day to be accommodated on the Brigg and Lincoln lines. These trains are essential to the UK economy as, among other goods, they carry oil for aviation fuel, steel which is critical for production process and rail works and coal to the power stations for electricity generation.
Mr Verster added: “The events leading to the disruption to rail services were entirely outside the control of the railway. We are working actively and tirelessly to minimise that disruption and to restore services as quickly as possible. Working with the colliery, we are making good progress on the repair which requires around a million cubic metres of material to be moved. We will continue to work with train operators to publish detailed timetables and information to allow passengers to plan their journeys.
“An important date for the railway is 20 July when work starts to fully upgrade the signalling and track layout at Nottingham station, further restricting the paths available for essential freight trains. The following week work is scheduled at Selby, blocking that route for trains. We continue to make every effort to complete the fix at Hatfield & Stainforth before these dates. However our train planners are also working with operators to develop a robust plan which can be used in the event that the repair at Hatfield is not complete. This includes making sure there is a viable route connecting Hull and east Yorkshire with Doncaster and the East Coast Main Line. Hull will not be cut off from the main network. Details of diversionary routes and alternative services will be published in the next three to four weeks.”
Currently affected operators First TransPennine Express and Northern Rail continue to work with Network Rail to keep passengers moving during the disruption. First TransPennine Express continues to explore the possibility of operating a limited weekend rail service via the Brigg route.
A spokesman for the companies said: "We appreciate the potential extension of the repair work is not ideal for our customers but it is imperative that Network Rail complete the works safely before handing the line back into service. Together, we are operating nearly 150 replacement buses a day between Doncaster, Hull, Scunthorpe and Cleethorpes and have additional staff at our stations to help with customer enquiries.
“Customer and community feedback is extremely helpful to us as we are continually assessing our plans to ensure we are providing the best possible alternatives.
"We would like to thank customers for their patience and understanding and assure them we are all working together to return rail services in the area as soon as possible."
Notes to editors
Current revised train times during the Hatfield & Stainforth disruption
First TransPennine Express services to Cleethorpes – replaced by buses between Doncaster and Scunthorpe.
First Hull trains running via Selby as usual
Northern Rail services between Leeds & Goole via Knottingley operating as normal.
Northern Rail services between Doncaster and Hull are diverted via Selby. Buses will serve intermediate stations between Doncaster and Goole. Train services are operating between Goole and Hull
Northern Rail services to Scunthorpe are replaced with buses between Doncaster and Scunthorpe.
Northern Rail services between Sheffield and Cleethorpes via Brigg which operate on Saturdays only are running as normal.
Freight services – approximately 150 services per day being diverted via a circular route over the Brigg Lincoln lines.
Proposed improvements to services above
The Brigg line is already highly congested because of the disruption but potential plans for a limited weekend service operated by First TransPennine Express are being explored. Further details of such will be released as and when plans are confirmed.
Please see attached Supporting information for details regarding limitations on the route and planned engineering acticvity, including Selby swing bridge and Nottingham.
Images from site will continue to be added to the online gallery here: http://www.networkrailmediacentre.co.uk/Gallery?SubjectID=653
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office -London North Eastern & East Midlands route
01904 383180
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk