The Gospel Oak to Barking line has reopened today (Wednesday 19 February) following completion of extensive repairs following a derailed freight wagon.

Just after 6am on Thursday 23 January, a freight wagon derailed between Leyton Midland Road and Walthamstow Queens Road on the Gospel Oak to Barking line which has caused extensive damage.

More than two and a half miles of the route between Barking and South Tottenham was damaged in the incident. Network Rail’s engineers have worked around the clock on a programme of repairs, clearing the damage, replacing 39 pieces of rail, 5300 concrete sleepers, 900 wooden sleepers, removing and replacing 10,000 tonnes of ballast during the track replacement and replacing custom-timbers at 10 bridges.

An investigation into the cause of the incident is ongoing.

Ellie Burrows, Network Rail’s route director for Anglia said: “Repairing and effectively rebuilding the railway has been an absolutely mammoth task for our engineering team, but along with great support across the industry and supply chain, I’m happy that train services can return to normal. I am acutely aware of the disruption this has caused for passengers and our lineside neighbours and I’d like to say thank you for bearing with us while we completed the work.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Katie Mack
Media relations manager (Anglia route)
0330 8577 132
Katie.Mack@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk