GO AHEAD FOR BETTER TRAIN SERVICES: A new viaduct to be built at Loughor

Friday 1 Jun 2012

GO AHEAD FOR BETTER TRAIN SERVICES

Region & Route:
| Wales & Western: Wales & Borders
| Wales & Western

A £40m plan to boost rail services in West Wales has been given the go-ahead with permission granted to replace a bridge on the main route between Swansea and Llanelli.

The plan will see the redoubling of six miles of track between Cockett West Junction and Duffryn West Junction, the re-instatement of the disused platform at Gowerton station, and the replacement of the Loughor viaduct.

Funding is split between Network Rail, which is paying for the £16m viaduct works, and the Welsh Assembly Government, which is behind the track redoubling.

The grade two listed Loughor viaduct has to be replaced as it can only bear the weight of one train at a time.

Listed building consent for work on the structure was received from Carmarthenshire Council yesterday (Thursday, May 31) and preparatory work will continue on site with the intention of opening a new bridge in mid-2013.

Network Rail is going to preserve some elements of the original viaduct and will rebuild two of the original spans on railway land to the west of the existing structure. It will also carry out a full photographic survey, so a record of the viaduct is available for future reference.

Route managing director for Network Rail Mark Langman said: “Replacing the Loughor Viaduct is the key to improving rail services to West Wales and we’re keen to get on with the work on this vital link.

“We appreciate the need to preserve our industrial heritage, we also have to provide the people of Wales with the best railway possible. In this instance we are working hard to keep some of the structure in place, whilst also taking care of the natural environment of the Loughor Estuary.

“The improvements to the railway between Llanelli and Swansea won’t just allow for more trains, they will also make the existing services more reliable and give the economy of the area a welcome boost.”

As the Loughor Estuary is a site of special scientific interest, the work has been planned in close communication with the Environment Agency for Wales and the Countryside Council for Wales to minimise any impact on the environment.

Two platforms will be installed on either side of the bridge to effectively turn the structure into a quayside. This will then allow a barge to be floated up the estuary to tie up next to the bridge. Another barge will be lowered in from the other side of the bridge. These will then sink pilings into the bed of the estuary so construction can continue around the operating railway.

All spoil will then be taken way, rather than pumped back into the water, protecting wildlife.

Thanks to the way the new structure will be built alongside the existing viaduct, the railway will only have to be closed for an estimated three weeks – planned for Easter 2013.

By that stage the foundations for the new structure will be in place in the estuary, with the replacement bridge deck next to the original, ready to be slid into place.

Notes to editors

The work is designed to bring economic benefits to west Wales by improving capacity between the key employment centres of Swansea, Llanelli, Carmarthen and further west. As well as providing the capacity to run two more trains to run between Swansea and Llanelli (and a further one train to Carmarthen) it means the trains that already run can do so with greater reliability.

From next Thursday (June 7) our project manager , will be available to show members of the press the viaduct and the works taking place there. Anyone interested in visiting should call Chris Denham on 020 33 56 9526 or email Chris.Denham@networkrail.co.uk

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office -Western route
MediaRelationsWestern@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk