Monday 9 May 2022
Glasgow's Argyle line reopens on time for passengers
- Region & Route:
- Scotland’s Railway: Scotland
The route between Rutherglen and Exhibition Centre has re-opened following a £32m improvement project.
Network Rail has successfully completed work to the Argyle line, which will reopen as planned this Monday (May 9) following an eight-week programme of extensive engineering works.
The line closed on March 13 to allow engineers to deliver a £32m investment in repairing and renewing tunnels, bridges and tracks between Rutherglen and Exhibition Centre
It was the most significant piece of engineering on the line in a generation and was all designed to improve punctuality and reliability for passengers for years to come.
Engineers removed 500 tonnes of concrete encasement from the tunnels, with 700 structural beams repainted and more than 1,000 square metres of waterproofing applied.
All ScotRail services affected by the work resumed in time for the start of Monday morning service.
Jenny Gilruth, Transport Minister, said: “Passengers will undoubtedly welcome the news that this particular programme of work and its associated closures have come to an end. I’d like to thank them for their patience throughout, particularly users of Anderston station. I would also like to thank all of the staff at Network Rail and ScotRail who have facilitated these improvements, delivering them on time and within budget.
“The Scottish Government has provided £32m of funding for this work and will continue to significantly invest in rail infrastructure and services in Scotland which helps us to attract passengers back to rail. It is vital that we deliver reliable infrastructure and do so in a manner that minimises the impact of disruption to passengers and freight.
“Any project of this scale brings with it a number of challenges but at the same time also delivers significant improvements to Scotland’s Railway for passengers, including a reduction in the need for future disruption arising from any future works.
Jeremy Spence, programme manager, Network Rail, said: “I am pleased that this major programme of work to the Argyle line has been completed both on time and within budget.
“The complexity of a project that covers multiple work sites, involves a range of disciplines, not to mention the mobilisation of plant and equipment, is not without significant challenges. It’s a credit to the Network Rail project team, our contractors and supply chain partners that every element was delivered safely and on time.
“The outcome is a comprehensive programme of improvements and enhancements that futureproof Scotland’s Railway for passengers, as work on this scale will not be required for many years to come.
“Closing part of our infrastructure is something done rarely, as we fully appreciate the impact of this on our customers. Our decision was weighed against whether it was best to complete the work over an intense period of time by closing the line completely or prolong it over many months by only being able to undertake work at weekends.
“I would like to thank all the passengers whose travel plans have been affected for their patience and understanding over the past eight weeks.”
David Simpson, ScotRail Service Delivery Director, said: “This was an ambitious programme of work and it’s great to see that it’s been completed on time, within budget, and with alternative transport arrangements working well for customers.
“The work has helped future proof the line and customers can look forward to a better journey experience.
“We’d ask them for a little bit more patience as we carry out further essential work at Anderston station over the next four weeks.
“We’ll be upgrading the entrance, booking office, concourse and platforms and installing a lift for better customer access.
“This is all part of our strategy to make ScotRail fit for the future with investment in infrastructure, more reliable timetables, and great offers like the half-price ticket sale which begins on 9 May.”
The Argyle line project includes improvements to Anderston station, with the closure of the station extended by four weeks until June 6. This is to allow engineers to complete critical work on the entrance, booking office, concourse and platforms.
By extending the closure, the most critical work will be finished earlier and reduces the overall time taken to renovate the station by 12 weeks, completing in the autumn instead of by December 2022.
Once complete, the station will feature a lift for better customer access, a remodelled booking office and modern finishes on the stairs, floors and ceilings. This also includes improving the outside area to the station, with a new-look glazed entrance and enhanced external lighting.
For up-to-date service information on the Argyle line, please visit https://www.scotrail.co.uk
If you have any questions about extending the closure of Anderston station, you can contact Network Rail’s 24-hour national helpline on 03457 11 41 41. For the latest and progress updates follow on Twitter @NetworkRailScot and @ScotRail.
Notes to Editors
The structural elements alone, including work at Andertson tunnel, saw engineers complete over 47,000 hours of work.
The slab track work was made up of 19 separate sites, ten of which were to replace damaged sections of the top slab ranging from two to eight metres in length. This work extends the life of the existing slab and also reduces the risk of temporary speed restrictions being imposed.
Principal contractors involved in delivery for the work include AMCO-Giffen, Story and Bam Nuttall.
Contact information
Network Rail press office - Eddie Harbinson
Senior media relations manager (Scotland)
07931866612
edward.harbinson@networkrail.co.uk
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.