Glasgow rail junction’s £4m Easter upgrade: Dawn near Glasgow

Thursday 18 Apr 2019

Glasgow rail junction’s £4m Easter upgrade

Region & Route:
Scotland’s Railway: Scotland

Network Rail will be delivering a £4m upgrade to a key junction on the southside of Glasgow this Easter.

Over the bank holiday weekend, Shawfield junction will be renewed with six sets of points (rails which move to transfer trains from one line to another) replaced and nearly 400m of new track laid.

Shawfield is a key junction on the west coast main line between Glasgow Central and London Euston - one of the busiest rail routes in Britain.

The upgrade being carried out this weekend will improve the reliability of the line and will mean the junction doesn’t need renewed for another 30 years.

Engineers will be working continuously around-the-clock from close of service on Friday night (April 19) until the early hours of Tuesday morning (April 23) to complete the project.

The team will use 11 engineering trains, and three specialist Kirow cranes to complete the job, with the existing infrastructure being cut up and removed before new track sections, which will be delivered in 50 pre-assembled panels, are laid.

Donald Morris, programme manager for Network Rail Infrastructure Projects, said: “Our engineers will be working hard to complete this complex programme as quickly as possible for passengers.

“The west coast main line plays a key role in the economic life of the country – carrying passengers and freight – and this work will help improve its reliability.

 “We understand the inconvenience this work may cause to some passengers and residents, but such a huge investment in the railway cannot be delivered without a short-term closure of the line.”

The upgrade is part of £18m-worth of improvements being delivered across Scotland’s railway this Easter by more than 1,500 engineers.

Further south on the west coast main line, engineers will be working to renew tracks and a level crossing and improve under-line drainage between Beattock and Abington in South Lanarkshire.

In the north east, engineers will be replacing or refurbishing seven bridges and improving drainage as part of plans to double-track the line between Aberdeen and Inverurie later this summer.

Most of the country’s services are unaffected by this weekend’s investment programme, but some routes, particularly in Lanarkshire and the North East, will see significant changes.

For more information about services over the Easter weekend, passengers can visit nationalrail.co.uk/Easter and follow #EasterRailWorks on Twitter.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk