Glasgow – Barrhead reopens to passengers following major upgrade works

Region & Route:
Scotland’s Railway: Scotland

The Glasgow - Barrhead line will fully reopen to passengers tomorrow morning, Friday 4 August, following a £63.3 million upgrade.

Since June 24, the line has been closed to allow engineers around-the-clock access to prepare the route for electrification as part of a Scottish Government investment to decarbonise the railway.

Over 70,000 hours were worked during the six-week closure and activity included installing 14,400 metres of overhead power cables (contact and catenary) and renewing 130 metres of track.

Bridge parapets were raised in height at Kennishead and Priesthill & Darnley stations to make them safe and compliant for an electrified railway.

A significant amount of work also took place at Barrhead station, with platform 3 extended to accommodate longer four-carriage electric trains. This involved moving the current buffers and rebuilding the access paths.

The old lattice footbridge at Nitshill station, too low to fit the overhead cables underneath, was replaced with a new ramp to platform 2 for services to Barrhead and Kilmarnock. It can now be accessed through a reopened underpass off Nitshill Road.

Paul Reilly, Network Rail Senior Programme Manager, said: “I would like to thank passengers, residents and businesses for their patience and understanding over the last six-weeks, as we delivered these vital engineering works.

“Electrification of the Glasgow - Barrhead line will transform travel by providing greener and quieter trains for our passengers.

“The work also represents another considerable achievement as part of our wider plans to deliver net zero across Scotland’s Railway and we’re looking forward to electric trains operating on the route.”

David Simpson, ScotRail Service Delivery Director, said: “It’s great to see that work to prepare the Barrhead line for electrification has been completed successfully and the route reopen for passenger service.

“We know how inconvenient it can be when extensive work like this is carried out, so we’re thrilled to be able to welcome customers back to the railway.

“I’d also like to thank everyone for their patience while this important upgrade was delivered.

“It’s an exciting project for Scotland’s Railway, with more of the network being electrified on our journey to net zero.”

Electrification represents a huge change to the railway environment on the line. Electrified lines carry 25,000 volts of electricity and are always on, so should be considered live and dangerous at all times.

Over the next few months, the team will be carrying out snagging and finishing works to the overhead line equipment, as well as replacing copes and tactile paving at Pollokshaws West station. This will be followed by signalling commissioning and running test trains on the route in the autumn, ahead of the introduction of electric trains from December.

While the Glasgow - Barrhead works were taking place over the six-weeks, Network Rail made the most of the opportunity by also delivering activity out with the project.

Refurbishment work to a number of signals took place south of Barrhead, near Lugton in East Ayrshire. Originally this would have taken three months working overnight but by doing this during the closure, the task was completed in half the time.

If you have any questions about the works, you can contact Network Rail’s 24-hour national helpline on 03457 11 41 41. For the latest information and progress updates follow on Twitter @NetworkRailScot or visit www.ScotlandsRailway.com

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk