Wednesday 12 Mar 2025

£14m upgrade works set to begin on Inverclyde lines

Region & Route:
Scotland’s Railway: Scotland

Engineers will be working around-the-clock on the Inverclyde lines between Saturday (March 15) and Tuesday (March 18) to deliver more than £14m of investment in renewing vital infrastructure.

Work will take place at a range of locations between Port Glasgow and Gourock and Wemyss Bay to renew track, refurbish structures and repair a tunnel on the railway.

Engineers will be renewing points – rails which move trains from one track to another – at Wemyss Bay Junction to the west of Port Glasgow station.

In Greenock work will be taking place to replace lineside walls between Cartsdyke and Greenock Central stations while a railway bridge over Sinclair Street in the town will also have its timber deck, which carries the track, replaced.

At Newton Street tunnel, which runs for over a mile between Greenock West and Fort Matilda stations, engineers will be carrying out stonework repairs and water-proofing the structure.

Due to the complexity of the projects involved, further work will also take place the following weekend (March 22 / 23).

To keep passengers on the move, replacement buses will run between Paisley Gilmour Street and Wemyss Bay / Gourock on March 15, 16, 17 and 18 and on March 22 and 23. Passengers can check their journey at ScotRail.co.uk or nationalrail.co.uk

Ross Moran, Network Rail Scotland route director, said: “This vital work will help improve performance and reliability for our customers. Our engineers will work around-the-clock to complete these projects as quickly as possible and we thank passengers for their understanding while this crucial investment takes place."

Mark Ilderton, ScotRail service delivery director, said: “These improvements will bring long-term benefits for ScotRail customers, ensuring a more reliable and resilient railway for years to come.

“We are fully committed to keeping customers moving and getting them where they need to be while this work takes place, with rail replacement bus services operating to minimise disruption.

“We appreciate our customers’ patience and encourage anyone planning to travel to check their journey in advance.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk