Project to make the railway safer and more reliable for passengers finishes.

A 10-week programme to renew track at Glasgow Central's platform 1 has been completed.

Passengers travelling through Scotland’s busiest station will now benefit from this £1.2m project which was undertaken to enhance the safety and reliability of the railway for years to come.

These essential works were part of the Scottish Government’s ongoing investment in Scotland’s Railway. The works included:

  • replacing 720 baseplates which are fixed to the concrete slab that holds the track in place
  • installing over 100 new timber sleepers along the length of platform 1
  • upgrading tactile paving along the platform edge
  • renew signalling cables
  • clean the buffers
  • deep clean of platform 1 and removal of overgrown vegetation

Had normal access arrangements been used, this work would have been spread over a period of approximately four years’ worth of Saturday nights and would have been considerably more costly.

Instead, this 10-week programme ran at the same time as the closure of Carstairs Junction so that disruption to passengers was kept to a minimum.

Tom Podger, Senior Project Engineer, Network Rail Scotland said: “Our team of engineers have been working around the clock to deliver this project safely and on time. Their work will improve the track at platform 1 as part of efforts to enhance the safety and reliability of the railway for years to come.

“We are pleased that the works have been completed on time and within budget.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk