FORTH BRIDGE MAKES FINAL BRUSH WITH A MODERN MYTH: Forth Bridge scaffolding and maintenance work

Monday 5 Sep 2011

FORTH BRIDGE MAKES FINAL BRUSH WITH A MODERN MYTH

Region & Route:
National

 

  • Painting due for completion by December

 

 

 

 

 

Network Rail and main contractor Balfour Beatty Regional Civil Engineering will preside over the end of a modern myth when painting of the Forth Bridge finally comes to an end this December.

After 10 years and an investment of over £130m, the bridge will finally be free of scaffolding, with a full paint job unlikely to be required again for over twenty years.

The current contract will be completed ahead of schedule on Friday 9 December 2011. A celebration event to mark the end of the refurbishment will take place in March 2012.

David Simpson, route managing director, Network Rail Scotland commented

“Network Rail is the proud steward of our railway history, which the Forth Bridge exemplifies. Since 1890 it has been a working monument to the genius of British railway engineering. Over the last decade, the bridge has been restored to its original condition and its new paint will preserve the steelwork for decades to come.

“The current restoration work has been ongoing since 2002 but, owing to years of underinvestment during the 70s and 80s, the scale of the job was initially unclear. Now, with scaffolding being removed and the final sections of painting being completed, we’re confident that job will be finished before Christmas.

“The paint system being used on the bridge has been used in the past on north sea oil rigs. We expect it to last in excess of twenty years but we will be back from time to time to maintain the most exposed sections of the structure.”

The current project involves more than the straightforward application of another layer of paint. Scaffolding access is erected and screened off from the environment before old layers of paint applied over the last 120 years are removed using an abrasive blasting technique. Steelwork requiring maintenance is then repaired before the new paint is applied in three protective layers.

Marshall Scott, managing director, Balfour Beatty Regional Civil Engineering, commented:

“Balfour Beatty is delighted to have played such a significant part in the restoration of the iconic Forth Bridge over the last 10 years.

“By working together in a close relationship, Balfour Beatty Regional Civil Engineering, Network Rail, the principal subcontractors and the workforce involved in undertaking this complex programme of restoration have successfully delivered a project requiring safe systems of work to overcome some of the most difficult of working conditions.

“The now fully restored Forth Bridge will continue to operate for many decades to come and it will provide the world renowned image that Scotland can be rightfully proud.

“The work that Balfour Beatty Regional Civil Engineering has provided to restore the Forth Bridge back to its original condition will remain as part of a legacy and a testament to the skills and expertise of those who built this much treasured structure more than a century ago”.

 

 

 

Notes to editors

…like painting the Forth Bridge (British)

If repairing or improving something is like painting the Forth Bridge, it takes such a long time that by the time you have finished doing it, you have to start again. ‘Home improvements are a bit like painting the Forth Bridge. By the time you've finished the kitchen, the bathroom needs decorating and so it goes on.’

Cambridge International Dictionary of Idioms © Cambridge University Press 1998

Forth Bridge facts

Age of Bridge: Opened 1890 (121 years old)

Length of Bridge

Overall: 2,467 metres

Main structure (portal to portal): 1,630 metres

Height of Bridge

High water to top: 110 metres

Foundation to top: 137 metres

Materials

Weight of steel in bridge: 53,000 tonnes

Number of rivets: 6.5 million

Concrete and masonry in piers: 120,000 cubic yards faced with 2ft thick granite

Operational information Number of trains per day: 200 Number of passengers per year: 3 million

Painting the bridge

Painting area: 230,000 sq metres

Volume of paint used: 240,000 litres

Lighting the bridge:

Total number of lights installed: 1040 lights

Length of cabling required: 35,000 – 40,000 metres

History:

1873 Thomas Bouch’s first design for a suspension bridge across the Forth presented

1879 Bouch’s design for the Forth Bridge abandoned following Tay Bridge disaster

1882 Design submitted by John Fowler and Benjamin Baker approved

1883 Construction of Fowler and Baker’s cantilever structure began

1885 Last caisson launched

1886 Pier foundations completed

1887 Three towers completed

1889 Cantilevers completed

1890 Bridge formally opened by Prince of Wales on 4 March 1890

  • 57 lives were lost during the construction of the Forth Bridge
  • At the height of its construction, more than 4,000 men were employed

The construction of the bridge resulted in an unbroken East Coast railway route from London to Aberdeen.


Contractors:

The main contractor is Balfour Beatty Regional Civil Engineering based in Edinburgh and is undertaking the restoration works with four principal sub-contractors – Pyeroy Ltd, specialists in blasting and coating ; Harsco Infrastructure, specialists in access systems and encapsulation; RBG Ltd, specialists in steel repairs, and ThyssenKrupp Palmers Ltd who facilitate for all three activities.

General:

Up to 320 people working on the bridge at peak times – many of whom are locally based.

Scope of the Works:

  • The painting process involves the erection of significant scaffold access systems to access the working areas and screening the area to be painted to prevent debris affecting or contaminating the surrounding environment.
  • Old paint is removed using an abrasive blasting preparation and the steel coated with an industrial protective coating system.
  • The paint used to coat the bridge is a specialist glass flake epoxy paint, similar to that used in the offshore oil industry and designed to last 25 years. It is, however, expected to last much longer.
  • WJ.Leigh of Bolton is the supplier of the specialist paint and coating systems
  • Repairs and replacement of walkways including the installation of new walkways and catwalks to allow for access to the works and to assist in the future examination and maintenance of the bridge.
  • Steel repairs - replacing small localised sections of steel where required
  • Refurbishment and maintenance of the architectural lighting system

Painting Method:

·

Essentially each section to be painted is surrounded by a scaffolding system and then encased in a “film like” encapsulation material.

The purpose of this is to capture all the debris from the removal of the old paint and from any steel repair work. This also provides a protected environment within which coatings can be applied and allowed to cure.

The project team is very conscious of its environmental responsibilities and have imposed stringent control measures to ensure that the surrounding environment – and the Firth of Forth – is protected from any contamination.

After thorough cleaning of the steel structure paint is applied both by airless spray and by hand in areas of particularly difficult access, each of the 6.5 million rivet heads are painted by hand.

The principal priority is safety of all the workforce and contractors working on the project and all the appropriate and specialist personal protective and specialist safety equipment is supplied and used for each and every activity, including regular health monitoring.

 

Work has progressed dependant on two key issues: the urgency of the repairs and balancing the scaffolding loads efficiently.

Currently the bridge supports approximately 4,000 tonnes of scaffolding access systems.

Area of steel requiring paint: 250,000m2

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk