Friday 26 Jan 2018

Fort William-Mallaig line to reopen on Monday

Region & Route:
Scotland’s Railway: Scotland

The rail line between Fort William and Mallaig will reopen on Monday (January 29) as engineers make good progress on repairing damage caused by a landslip near Glenfinnan.

Over 1,000tonnes of stone and mud was deposited on the track after the mountainside above the railway gave way over night on Sunday into Monday (January 22).

Engineers have now cleared the material away from a train which struck the landslip, rerailed the vehicle using specialist machinery and removed it from the incident site.

Over the next two days they will install extra drainage around the area, make repairs to the track and undertake further work to secure the slope above the line.

David Dickson, ScotRail Alliance infrastructure director, said: “Our engineers will be working hard throughout the weekend to reopen the line for customers.

“The recovery operation is progressing to plan and we remain confident that we will be able to reopen the line for customers from the start of service on Monday.

“The isolated location, and steepness of the slope above, has made this a complex recovery operation and we are grateful to customers for the patience they have shown during this period of disruption.”

A replacement bus service remains in operation between Fort William and Mallaig to keep passengers on the move.

Customers affected by this issue can use ScotRail’s Delay Repay compensation scheme, which kicks in for services that are delayed for 30 minutes or longer. Full details on this can be found at scotrail.co.uk/delay-repay

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk