Fort William-Mallaig landslide recovery update: Fort William - Mallaig1

Friday 12 Aug 2016

Fort William-Mallaig landslide recovery update

Region & Route:
Scotland’s Railway: Scotland

The rail line between Fort William and Mallaig will remain closed over the weekend as engineers work to repair damage caused by a landslip near Lochailort.

Over 100 tonnes of stone and mud was deposited across 70m of the track after the mountainside above the railway gave way on Thursday evening.

Trains between Glasgow Queen Street and Mallaig are terminating at/starting from Fort William while engineers work to divert floodwater away from the line, clear the debris and repair damage to the infrastructure beneath.

A replacement bus service is in operation between Fort William and Mallaig to keep passengers on the move.

A ScotRail Alliance spokesman said: “Our team has been on site since Thursday assessing the damage and making repairs. We are working to get the line open as soon as possible, but significant repairs will be needed to fix the damage caused to both the railway and slope above.

“We are grateful to customers for their patience during the disruption. Buses are running in place of trains between Fort William and Mallaig to help keep people on the move. However, roads are also affected by the landslip and divisionary routes may be used, meaning extended journey times. We apologise to customers who are affected by this disruption.”

Engineers expect to take around 48-hours to clear material from the line, replace washed away ballast beneath the track and then carry out work to stabilise the slope above the line to minimise future landslip risks.

Customers affected by this issue can use ScotRail’s Delay Repay compensation scheme, which kicks in for services that are delayed for 30 minutes or longer. Full details on this can be found at scotrail.co.uk/delay-repay

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk