Friday 26 Jul 2024
Five days of major changes to Chiltern main line journeys start tomorrow
- Region & Route:
- North West & Central
- | North West & Central: Central
Chiltern Railways passengers are being reminded to check before they travel ahead of a five-day closure of the Chiltern main line between Bicester and Leamington Spa which starts on Saturday 27 July.
As part of a £9m+ investment, Network Rail and its partners at Story Contracting will work around the clock until Wednesday 31 July to replace a bridge which carries the railway over the River Cherwell in King's Sutton near Banbury.
During the closure engineers will lift a new 240-tonne bridge deck into place using two special rail-mounted ‘Kirow’ cranes. Once complete the work will keep the structure safe and reliable for passengers and freight services for decades to come.
At the same time engineers will upgrade over 500 metres of railway north of Banbury station which includes replacing sections of track and drainage to help make journeys smoother.
While the work takes place the railway will be closed between Bicester and Leamington Spa stations, with services resuming on Thursday 1 August.
To keep passengers moving railway replacement buses will operate as follows, connecting with trains to/from Marylebone at Bicester Village, and connecting with trains to/from Birmingham Moor Street at Leamington Spa:
- Bicester Village - Banbury - Leamington Spa.
- Bicester Village - Banbury - Stratford Upon Avon.
- Bicester Village - Kings Sutton - Banbury.
Adam Checkley, infrastructure director for Network Rail, said: “I’d like to thank passengers for their patience while we complete over £9m of upgrades on the Chiltern main line between Bicester and Leamington Spa stations over the next five days to help make journeys more reliable.
“If you're planning to catch a train during the rail closures, please check with Chiltern Railways and at www.nationalrail.co.uk before you travel for information about your journey.”
Andy Camp, commercial and customer strategy director at Chiltern Railways, said: “These crucial engineering works will ensure more reliable journeys for customers in the future and I would like to thank customers for their understanding as this work will mean they will need to change their normal travel plans during this period.
“There will be no through trains between London Marylebone and Birmingham during the five-day closure. Journeys will be longer and may include travel on a rail replacement bus so I urge customers to check their journeys before setting out.”
On Saturday 27 and Sunday 28 July Network Rail is also replacing a section of track to the south of Oxford at Culham, and continuing preparations for the construction of the new platform for the station as part of the Oxfordshire Connect station expansion programme.
Passengers should check www.chilternrailways.co.uk/jul24engineering for journey information and travel advice.
Notes to Editors
Other general travel advice for customers travelling during the rail closure:
On Saturday 27 July, Bruce Springsteen will be performing in concert at Wembley Stadium. An enhanced timetable will be in operation during the afternoon and evening, with additional Wembley Stadium stops in trains, and also some additional trains. Services will be busier than usual due to additional passengers travelling because of engineering work between Oxford and Didcot.
A reduced service of one train per hour will operate between Marylebone and Aylesbury Vale Parkway between 12:00 and 20:00. After 20:00 rail replacement buses will operate as follows, connecting with trains to/from Marylebone at Beaconsfield:
Beaconsfield - Amersham - Great Missenden - Wendover - Stoke Mandeville - Aylesbury - Aylesbury Vale Parkway.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk