First train runs on Midlands’ newest and longest railway bridge: First train over SAS 13 bridge-2

Monday 23 May 2022

First train runs on Midlands’ newest and longest railway bridge

Region & Route:
North West & Central
| North West & Central: Central

The Midlands’ newest and longest railway bridge is now fully functional after carrying its first freight train.

Tracks reopened today (Monday 23 May) on the Stechford to Aston freight line in Birmingham following the installation of a massive 2,600-tonne bridge* built by Network Rail in partnership with HS2.

At 92 metres long, the steel and concrete structure becomes the longest single span railway bridge in the Midlands.

It needs that clearance underneath so future tracks for Britain’s new zero-carbon railway can be built below for HS2 trains to access its Washwood Heath depot.

The demolition of the old railway viaduct and installation of the new bridge has closed this connection to Birmingham rail freight terminal for 23 days.

But today the first train passed over the new structure, reopening the important rail freight route and marking a huge milestone for project contractor Skanska.

Patrick Cawley, director for ‘On Network Works’ for Network Rail and HS2, said: “Seeing the first train pass over this iconic structure is a proud moment for the hundreds of people who’ve worked throughout the pandemic to make this new bridge a reality.

“It’s also a key part of the jigsaw to ensure the existing railway network works in harmony with HS2. I’m conscious this work has disrupted some passenger journeys over recent weeks and I’d like to thank CrossCountry customers for their patience while we carried out this major project.”

Rosario Barcena, Skanska Rail programme director, said: "Installing a railway bridge over an existing railway line is a complex engineering project that requires a huge amount of skill and dedication from all those involved. To have delivered this on time and despite of Covid-19 restrictions is a fantastic achievement and testament to the team involved."

Building and installing the bridge, known as SAS 13, involved precision planning and engineering and the use of some heavy-duty equipment.

Earlier this month the structure was driven into place by remote-controlled vehicles after being pre-assembled on site in a civil engineering project which has taken over two years.

Building it on site reduced carbon emissions and cut the number of lorry movements on local roads, minimising impacts on the local community.

CrossCountry passengers are being given advanced notice of future work later in the summer on the same Birmingham New Street to Coleshill Parkway route.

Journeys will be impacted by more work to ready the railway for HS2 at weekends in August and early September.

Over four consecutive weekends from 13 August to 4 September, work will take place to:

  • Upgrade railway signals at Washwood Heath
  • Install piles in preparation for a new underbridge at Duddeston
  • Engineering work on a bridge at Heartlands Park
  • Carry out maintenance activity on this section of railway to make it more reliable.

To carry out the work safely, CrossCountry services between Birmingham New Street and Coleshill Parkway will be replaced with rail replacement buses.

Some long-distance services will also be diverted which means journeys will take longer.

Network Rail is working with CrossCountry to keep people informed.

Passengers should plan their journeys in advance at www.nationalrail.co.uk

Notes to Editors

*With the tracks and ballast now finished on top of the bridge, the total weight of the structure is 3,200 tonnes.

In numbers, the SAS 13 bridge:

  • Weighs a total of 2,600 tonnes (3,200 with the railway weight now on top)
  • Spans a distance of 92 metres
  • Is held together by 26,715 bolts weighing a total of 25 tonnes
  • The whole project uses 3,601 cubic metres of concrete
  • And 1,118 tonnes of steel (equivalent to 940 Mini Cooper cars)
  • Is an investment of £85m to ready the existing railway for HS2

End to end the new metal bridge is 92 metres long – four metres shorter than London’s Elizabeth Tower – the home of Big Ben.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk