First part of 21-day railway closure set to begin in one week to allow Network Rail to complete vital reliability upgrade to the West of England Line between Yeovil Junction and Axminster: Engineers working by Honiton Tunnel (2) (1)

Monday 30 Oct 2023

First part of 21-day railway closure set to begin in one week to allow Network Rail to complete vital reliability upgrade to the West of England Line between Yeovil Junction and Axminster

Region & Route:
Southern
| Southern: Wessex

The first of a two-part closure of the West of England line will see the railway closed for five days between Yeovil Junction and Axminster starting next week followed by a 16-day closure between Salisbury and Yeovil Junction in late November.

The first closure will take place in one week from Monday 6 to Friday 10 November between Yeovil Junction and Axminster, where engineers will be working around the clock completing key upgrades at four different worksites as part of a wider half a million-pound investment to improve reliability and performance along the West of England Line.

At Crewkerne tunnel, engineers will be continuing efforts to stabilise the cutting following a landslip in October 2021. Specialist six-metre-long soil nails will be drilled into the earth just outside the tunnel entrance, as well as the installation of new drainage to help reduce the impact of heavy rainfall.

Other work includes replacing the barriers at Broom and Axe level crossing, painting Weycroft River Bridge with a protective, anti-corrosion paint, and removing wet beds (areas of waterlogged track stones that cause rough rides for trains) at Crewkerne level crossing.

The second, 16-day closure between Salisbury and Yeovil Junction will take place from Saturday 25 November to Sunday 10 December.

Around 1280m of track between around Tisbury and Sherborne and 457m of track running through Gillingham station platform one will be replaced and then recycled. Engineers will also be clearing vegetation between Tisbury and Gillingham, completing level crossing maintenance at Wyley and Castleton level crossing and stabilising earthworks by Gillingham tunnel.

Mark Killick, Network Rail’s Wessex route director, said: “Over the past three years, we’ve worked really hard to improve the reliability and resilience of the West of England line by strengthening the cuttings and renewing old worn-out sections of track.

“Next month, this two-part closure will enable our engineers to continue these important upgrades as part of our continued programme of investment on this line. I fully recognise that every time we close the railway it is disruptive for our customers, and we always work hard to find the time when it inconveniences the least number of people.

"These upgrades are crucial for the safe and reliable running of services on the West of England line in the future and I’m grateful to customers for their patience and understanding during this time.”

Peter Williams, South Western Railway's customer and commercial director, commented: “The closures on the West of England Line in November and December will allow Network Rail to carry out vital maintenance and improve reliability and performance on this part of our network.

“Between Monday 6 and Friday 10 November, rail replacement bus services will operate between Yeovil Junction and Axminster, with a revised train service from Axminster to Exeter St Davids.

“While the line between Salisbury and Yeovil Junction will be closed between Saturday 25 November and Sunday 10 December, customers will still be able to travel on our services between London Waterloo and Exeter St Davids, as services will be diverted via Westbury.

“Rail replacement bus services will be in place for customers travelling to Tisbury, Gillingham, Sherborne and Templecombe. Customers are also advised that services between London Waterloo and Salisbury, Basingstoke and Salisbury, Yeovil Junction and Exeter St Davids, and Reading and Salisbury, will all be altered over these 16 days.

“We appreciate our customers’ patience and advise them to check before travelling at southwesternrailway.com/plan-my-journey.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Tala Ghannam
Media Relations Manager (Campaigns) - National
Network Rail
07548 108907
tala.ghannam2@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk