Wednesday 26 Mar 2014
First new platforms to open at London Bridge as Thameslink programme gathers pace
- Region & Route:
- | Southern
The first phase of the dramatic rebuild of London Bridge railway station is set to finish on schedule next Monday (31 March) when the first two new platforms will be brought into use and the next two are closed for redevelopment.
London Bridge is one of Britain’s busiest stations, serving 54m passengers a year, and is getting busier. The current layout of the station and the tracks surrounding it mean that currently no more trains can run during the morning or evening peak periods.
The station is being redeveloped as part of the government-sponsored £6.5bn Thameslink Programme, which will transform north-south travel through London. The investment will remove bottlenecks to enable new, more spacious trains to run with Tube-like frequency every 2-3 minutes at peak times through central London by 2018, reducing pressure on the Underground. Better connections will offer passengers more travel options to new destinations while new track and modern trains will make journeys more reliable.
The overhaul of London Bridge - Britain’s biggest ever station redevelopment - will result in a bigger, brighter, station that is unrecognisable from today. When complete the station will be longer than the Shard is tall, with a new single concourse larger than the pitch at Wembley at street level to provide more space and easier connections to other rail services and the Underground. Improved links will join the two communities to the north and south of the station and help boost economic regeneration in the area.
The entire length of the new, longer platforms at London Bridge will be covered by strikingly-designed undulating canopies of steel and aluminium, allowing passengers to make full use of them during all weather conditions, making boarding trains more efficient. Stunning ‘eyebrow’ arches over north-facing glass will let light flood the platform and the new concourse being built directly below.
Dave Ward, Network Rail route managing director, said: “This huge investment in rebuilding London Bridge station will transform rail travel in London for millions of people across London and the south east. By 2018, London Bridge will be the most modern station in Britain with more space, better connections and great facilities.
“Keeping London Bridge open for passengers while we rebuild it is a critical and challenging part of the Thameslink Programme. Construction goes on as much as possible behind the scenes without impacting passengers but there will be times each year between now and 2018 where services into the station will need to change.
“Wherever possible, we will schedule work that requires changes to train services at quieter times, such as summer holidays and Christmas, to minimise disruption as much as possible.”
Chris Burchell, Southern’s managing director said: “The opening of the first two new platforms at London Bridge demonstrates real progress in the huge transformation programme for the station. They also offer passengers, who have been living with the reduced capacity at the station for some months now, an initial glimpse of the future benefits when the wider programme is complete. There is much more work still to do affecting Southern passengers at London Bridge in 2014 for which detailed information on travel options are being provided – particularly for the partial closure on 28 March as well as the longer closures between 23 and 31 August and 20 December and 4 January 2015. We are grateful to passengers for their support and patience over this period.”
David Statham, First Capital Connect managing director, said: “The Thameslink Programme and Network Rail’s rebuilding of London Bridge is going to give the Thameslink route its own dedicated platforms and a fabulous high frequency service.
“Inevitably this means service changes, with diversions for Thameslink trains around London Bridge in August and for a further three years from December. So we urge people to log on to ThameslinkProgramme.co.uk to find out what’s happening and to plan ahead.”
Rail Minister Stephen Hammond said: “Thameslink is vital if we are to deliver a transport network fit for the 21st century, providing more seats across the morning peak and better connections across the south east. The London Bridge redevelopment is at the heart of this project and I am pleased to see progress is being made with the opening of these two new platforms. Whilst there will be disruption, the benefits to passengers in the long term will be tremendous.”
2014 station and service changes are available on ThameslinkProgramme.co.uk affecting the folowing dates:
March 28-31; August 23-31 and December 30, 2014 in to January and onwards.
Alternative routes are available for all passengers during these periods but knock-on effects across London and the South East are expected.
Ends
Notes to editors
Notes to Editors
Friday 28 March
- Southern services at London Bridge will be reduced after the morning peak
Saturday 29 March
- No Southern services or First Capital Connect will call at London Bridge
Sunday 30 March
- No Southern services or First Capital Connect will call at London Bridge
- Southeastern trains to and from London Charing Cross are being diverted to start/terminate at London Cannon Street. A shuttle service will run between London Charing Cross and London Cannon Street, calling at Waterloo East.
Monday 31 March
- Some minor amendments to Southern services in the early hours
Information on service changes, resulting from further works will be promoted in late Spring by Network Rail, train operators and TfL to ensure passengers are kept fully informed.
Contact
Thameslink Communications Team
contact@thameslinkprogramme.co.uk
07515 618204 or 07515 617622
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk