Fascinating drone footage reveals extensive damage on Conwy Valley Line: Conwy Valley Line March 2019

Friday 22 Mar 2019

Fascinating drone footage reveals extensive damage on Conwy Valley Line

Region & Route:
Wales & Western: Wales & Borders
| Wales & Western

Drone footage released by Network Rail Wales and Borders shows the extensive damage caused by Storm Gareth on the Conwy Valley Line. The line, which runs between Llandudno Junction and Blaenau Ffestniog, will remain closed for a number of months.

Detailed inspections undertaken this week revealed that multiple sections of track, lineside equipment, embankments, bridges, level crossings and stations require significant repairs. Specialist engineers are now putting a detailed programme of work in place to restore the line as quickly and safely as possible for passengers.

Bill Kelly, route managing director for Network Rail, Wales and Borders, said: “We apologise to passengers and the local community who have been affected by the Conwy Valley Line closure following extensive damage caused by Storm Gareth.

"We are working closely with our partners, Transport for Wales, to keep passengers moving with rail replacement buses during the closure of the line.  We recognise the importance of the Conwy Valley Line to local people, businesses and communities. We will continue to work closely with the local Community Rail Partnership and other stakeholders and provide regular updates as the work progresses."

James Price, Transport for Wales CEO added: “We now understand the extent of the damage caused by Storm Gareth to the Conwy Valley Line and we will be working collaboratively with our partners in Network Rail to ensure we keep the people of Wales moving.

"We encourage our customers to regularly check for service updates and we will provide information as work on the line progresses.

"We apologise to those who have been affected by the closure. ”   

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Bryony Parry
Media Relations Manager
07734 649220
Bryony.Parry@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk