Extension work on-track for Milngavie Station: Milngavie platform works

Thursday 5 Nov 2020

Extension work on-track for Milngavie Station

Region & Route:
Scotland’s Railway: Scotland

Network Rail has successfully completed three weekends of construction work at Milngavie as part of a £5m investment to extend the platforms at the station.

At the weekend (on Sunday, November 1) the project team installed a new 4m-tall twin-track stanchion to support new overhead line equipment at the remodelled station.

Over the previous two weekends (On Sundays October 18 and 25), engineers successfully installed new precast platform sections onto the 24-steel foundations laid to support the extended infrastructure.

Once complete in December this year, the station’s platforms will have been lengthened from 141m to 205m. The works, being undertaken by Network Rail and main contractor AmcoGiffen, will also deliver changes to the track and signalling layout at the station.

Extending the platforms will enable the ‘stabling’ of trains at Milngavie to allow more time between arrivals and departures. This will help improve punctual delivery of the timetable and improve service reliability.

Kevin McClelland, Network Rail route delivery director for capital delivery, said: “Our team has been working hard to deliver this important part of the platform extension project as quickly as possible and with a minimum of disruption for our customers.

“We understand the inconvenience this work may cause to some passengers and also to our lineside neighbours living closest to the station and I would like to thank them for their cooperation and patience while we deliver this £5m investment in their station.”

David Simpson, ScotRail operations director, said: “When complete, the extension of the platforms will help deliver greater resilience on a significant route on central Scotland’s railway and in doing so, provide improvements in the service we can offer to passengers.

“Everyone on Scotland’s Railway is working hard to keep the network running during this difficult time for the country and to continually improve the service we offer by investing to improve punctuality and reduce delays.”

For further information about the work, lineside neighbours can call Network Rail’s 24-hr helpline on 03457 11 41 41 or contact milngavieplatforms@networkrail.co.uk.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk