Euston station fully reopens after six days of major railway upgrades: PHOTO Network Rail teams on site with tamping trains in the background Willesden Junction Easter 2026

Thursday 9 Apr 2026

Euston station fully reopens after six days of major railway upgrades

Region & Route:
North West & Central
| North West & Central: West Coast Mainline South

The West Coast Main Line has reopened to passengers after six days of major railway improvements between Milton Keynes and London Euston.

Today (Thursday 9 April) trains started running again after multiple projects to upgrade stations, tracks, signalling systems, overhead power lines and bridges took place, representing an ongoing investment of £46.7m.

The journey-improving work carried out by Network Rail and its supply chain over the Easter period include:

  • £8.4m replacing track, switches and crossings (S&C) and railway foundation stone (ballast) at a complex railway junction in Willesden, North West London*
  • A £6.6m bridge deck replacement and waterproofing project at Ledburn near Leighton Buzzard
  • £7m of signalling upgrades in Ledburn to make the system more reliable and reduce delays
  • Over £8m renewing overhead lines which power trains through Wembley
  • £2m of enabling works started in Bushey as part of a two-year project to boost power supplies to run more electric trains in and out of London in future
  • A £5.8m investment started at Harrow & Wealdstone to waterproof station canopies and renew platform edges
  • Piling and underground utilities work at Apsley station as part of the £8.9m Access for All scheme to install three new lifts onto the existing footbridge and make the station fully step-free this year

In addition, teams based in the North West of England completed signalling and overhead line upgrades between Preston and Oxenholme last weekend (4 and 5 April).

The work on the southern section of the West Coast Main Line is part of a wider £400m investment into Europe’s busiest mixed-use passenger and freight railway over the next several years.

Meanwhile passengers planning journeys on the line north of Preston between Saturday 11 and Sunday 19 April are being reminded of more journey-improving upgrades which will impact travel.

That will see overhead lines replaced over eight days between Preston, Lancaster and Fylde.

Once again Network Rail and train operators have worked together to keep passengers on the move – trying to keep them on trains for the majority of their journeys where possible.

Avanti West Coast will divert trains on the iconic Settle & Carlisle line. Replacement buses and some limited train services will also run.

Passengers are urged to plan their journeys in advance by checking www.nationalrail.co.uk.

Christian Irwin OBE, Network Rail North West and Central region Capital Delivery director, said: “I’d like to thank passengers for their patience while we’ve been carrying out these major railway upgrades between Milton Keynes and Euston over the last six days.

“We were able to use that time to carry out some really complex and important projects which are only possible during a full railway closure. These are all part of our commitment to investment hundreds of millions of pounds into the West Coast Main Line by upgrading tracks, stations, overhead power lines, structures and signalling systems to keep the railway running smoothly, safely and reliably in the years to come.”

For more information on how Network Rail maintains and upgrades the railway you can visit: https://www.networkrail.co.uk/our-work/looking-after-the-railway/

Notes to Editors

*A temporary speed limit is in place over the newly installed track at Willesden Junction meaning trains are travelling over the new infrastructure at a slower speed of 20mph, with a view to increase that to 50mph this evening. As is standard practice after such a significant renewal, that 50mph could be in place for several weeks while the new infrastructure beds in and follow up railway foundation stone settling work using trains called tampers can take place, although will be regularly reviewed and lifted sooner if possible.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk