Essential track renewals on the Crouch Valley line
- Region & Route:
- Eastern: Anglia
Network Rail will replace 50 plus year old rails and sleepers between Battlesbridge and Southminster during a seven day programme of essential renewals in August, helping to maintain a safe, reliable and comfortable railway for passengers.
Customers planning to use Greater Anglia services from Saturday 22 August to Friday 28 August 2026 are being encouraged to check before they travel and to leave extra time to complete their journeys.
Track replacement work will take place along the Crouch Valley line, including significant maintenance of the railway and stations while the line is closed:
- Inspecting and maintaining railway infrastructure between Wickford and Southminster, including bridges, overhead line equipment and signalling systems, to help keep train services safe and reliable.
- Improving drainage along the route to reduce the risk of flooding
- Clearing vegetation to minimise delays caused by overgrown trees and plants which can create a risk to the safe operation of the railway.
- Replacing ageing buffer stops at Southminster station to improve safety at the end of the railway line.
- Repairing part of the platform at Burnham-on-Crouch station, helping to maintain a safe and reliable station environment for passengers.
Rail replacement buses will operate between Wickford and Southminster from Saturday 22 August 2026 to Friday 28 August 2026 from the following locations:
- Wickford: Outside the front of the station.
- South Woodham Ferrers: Hulbridge Road.
- North Fambridge: Fambridge Road, at the junction with station approach.
- Althorne: Fords of Althorne forecourt.
- Burnham-on-Crouch: Station car park.
- Southminster: Station forecourt.
NOTE: Customers wishing to use Battlesbridge station should use the nearest alternative station as rail replacement buses will not operate from Battlesbridge
Joe Kennedy, infrastructure director for Network Rail Anglia said: "This essential work will help keep trains running safely and reliably on the Crouch Valley line for years to come. We're replacing rails and sleepers that are more than 50 years old, alongside a range of other improvements across the route, to help reduce future faults and disruption for passengers.
"We're sorry to passengers whose journeys will be affected while this work takes place, but replacing track of this age requires an extended closure so our teams can carry out the work safely and efficiently.
"There's never an ideal time to close the railway, but we always plan these projects carefully to deliver the improvements the railway needs while minimising disruption as much as possible."
Network Rail Anglia, Greater Anglia and c2c are working together as GBR Anglia, bringing track and train closer together to improve planning, strengthen day-to-day coordination and deliver a more joined-up railway for customers across the region.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Dakshin Kumudhini
Communications Manager
Network Rail
dakshin.kumudhini@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk