Network Rail engineers are today starting work to try and prevent any further damage to the railway at Dawlish in Devon as another Atlantic storm system is forecast to hit the south-west of England on Saturday.
Around 80m of sea wall has been destroyed by high tides and stormy seas, causing a significant stretch of railway to collapse into the sea. The road adjacent to the railway and several houses have also been significantly damaged, along with damage at Dawlish station itself.
Network Rail has mobilised a range of specialist contractors, engineers and suppliers from across the country to help with the work needed at Dawlish and has also taken up the offer of discussions with the Ministry of Defence to see if there is any help which can be provided by armed forces personnel based in the south-west.
Initial estimates are that it will take at least six weeks to reopen the railway, but the immediate priority is to shore up the damaged section on Thursday and Friday using a concrete spraying machine which was until recently being used to refurbish Whiteball Tunnel in Somerset.
A period of calmer weather is predicted once the weekend’s storm system has passed, which will enable Network Rail and its partners to fully assess the damage and how long it will take to begin the task of rebuilding the railway.
Network Rail’s route managing director for the Western route, Patrick Hallgate, said: “We absolutely understand the importance of the railway to the south west and will do everything we can to rebuild the railway at Dawlish as quickly and safely as we can.
“After a quieter night’s weather, we have been able to begin delivering machinery to our site compound with a view to protecting the exposed section of railway and the land behind it. We need to make sure we limit any further damage this weekend so that the significant repairs that are needed do not become greater still.
“We will continue working with the Government, Environment Agency, local authorities and other partners to explore ways of improving the railway’s resilience to extreme weather. The disruption to rail services in the south-west highlights the importance of that work and the need for all forms of transport to ensure that they are fit for the future.”
In addition, engineers are on site at a number of locations in the south west of England and are making repairs where the weather conditions permit. Services have resumed between Plymouth and Newton Abbot, but there will be no trains east of Newton Abbot to Exeter until the line is repaired at Dawlish.
Notes to editors
Further photos of the damage at Dawlish can be found here: bit.ly/LSxX2Q
Timeline:
Tuesday, 4 February – Weather forecasts predict a major storm off the coast of Devon and Cornwall. Network Rail marine buoys predict ‘black’ storm conditions, with six-metre waves. This is the first ‘black’ conditions predicted since the system was installed in 2007.
3.15pm – The line through Dawlish is closed to trains and staff withdrawn to safe locations.
Serious overtopping by waves is reported through the evening.
9pm onwards, damage reports received concerning both the railway and the adjoining land.
11pm-2.30am Inspections confirm extent of severe damage.
Wednesday, 5 February – Engineers on site at first light but unable to inspect the line due to contiuning storm conditions. Teams of engineers, contractors and suppliers mobilised and head to Dawlish. Work begins on site compound to store machinery to shore up damage, including spray-concrete equipment.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk