End of the line for Borders rail installation: Borders final rail installation

Thursday 12 Feb 2015

End of the line for Borders rail installation

Region & Route:
Scotland’s Railway: Scotland

The installation of almost 30 miles of rail on the new Borders Railway was officially completed today (Thursday, February 12) when Keith Brown, cabinet secretary for infrastructure, joined the project team to clip the final length of rail into place.

Arriving by rail at Tweedbank station, on the first train to reach the end of the new line, Mr Brown clipped the final rail into place alongside Hugh Wark, Network Rail’s project director.

Since track-laying commenced in October last year, over 1000 rails have been laid across more than 90,000 sleepers using a specialist rail installation machine.

The longest new domestic railway built in Britain in over a century, the Scottish Government-funded Borders Railway will re-establish passenger services for the first time in over 40 years from Edinburgh through Midlothian to Tweedbank.

Mr Brown said: “It is a huge honour to put the final piece of track in place and travel on the first train to run into the Borders in almost half a century. The reopening of this line offers a once in a generation opportunity to deliver a major economic and social boost for the communities it will serve.

“In just a few short months, trains will be carrying passengers to employment, social and study opportunities, as well as bringing visitors and investors to the communities all along the route. We can expect the Scottish economy to benefit by tens of millions of pounds from its reopening and the area around the railway line will be an exceptional tourist destination, with a steam railway service, National Mining Museum Scotland, world-class exhibition spaces, and the Great Tapestry of Scotland displayed at Tweedbank.

“This is the longest domestic railway to be built in Britain in over 100 years and is a fantastic engineering achievement for Scotland and for the rail industry. But more importantly, the Borders Railway is the realisation of a long-held aspiration that will see community links restored, local economies boosted and opportunities improved for many.

"There will be few, if any, railway journeys anywhere in Europe to match the outstanding scenery along the route of the new Borders Railway. I have no doubt that Borders Railway will be hugely successful, both in enhancing Scotland’s infrastructure and transforming business opportunities along the line.”

Hugh Wark added: “The completion of rail installation is a major milestone for the project and keeps the line on-track to open for passengers in September. While we still have a significant amount of infrastructure to complete along the route – from installing signalling to completing the stations – we're confident that this much-anticipated addition to Scotland’s railway will be delivered on schedule.”

With the rails now in place, the project team will focus on completing ballast spreading, tamping and welding on the track, installing signalling and communications equipment and completing the construction and fit-out of seven new stations – at Shawfair, Eskbank, Newtongrange, Gorebridge, Stow, Galashiels and Tweedbank.

With construction due to complete in the summer and the line to enter service in September 2015, the new railway will offer a fast and efficient alternative to the congested local road network allowing passengers to travel from Tweedbank to Edinburgh in around an hour at peak times.

The railway is expected to deliver major economic and social development opportunities – connecting people to jobs, housing, leisure opportunities and other facilities. The project is a key part of the Scottish Government’s wider programme of investment in transport infrastructure, working towards the sustainable economic growth of Scotland.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Scotland
0141 555 4109
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk