Despite the severe weather over the past month, eight out of 10 trains still ran to time and almost 92%, or 19,000 each weekday, of scheduled services ran.
The figures were released today in Network Rail's regular monthly report on train performance that, during the four weeks from 13 December to 9 January, 80% of services arrived on time. This compares to 89.8% in period 10 last year.
Train punctuality was affected by the severe weather with a reasonable service being provided on almost all routes. Punctuality did drop during the extreme cold snap but underlying performance remains at historically high levels with, on average over the past 12 months, 91.2% of services arriving on-time.
Robin Gisby, director of operations and customer service, said: “It's been a difficult month and we have not delivered the railway passengers have come to expect. Working closely with the operators, and despite the extreme weather, we have kept the railways open and most services ran with eight out of 10 services running to time. We will work to restore services to their punctual norm in the weeks ahead."
Only two of the 19 operators - London Midland and East Midlands Trains - saw their performance improve compared to the same period last year. London Midland saw the biggest improvement in performance this month compared to the same period last year. Sixteen operators saw significant movement in their performance (over three percentage points):
Operator P10 2009 P10 2008 % point change Southeastern 70.0% 91.7% -21.7% East Coast 67.2% 88.4% -21.2% First Capital Connect 72.8% 93.0% -20.2% First Scotrail 72.9% 88.9% -16.0% First Transpennine Express 75.7% 90.5% -14.8% National Express East Anglia 78.5% 92.0% -13.5% South West Trains 82.2% 93.8% -11.6% Southern 77.8% 88.9% -11.1% Crosscountry 77.0% 87.5% -10.5% Virgin Trains 65.7% 75.7% -10.0% Chiltern 89.4% 95.8% -6.4% First Great Western 85.9% 91.9% -6.0% London Midland 83.4% 78.9% +4.5% London Overground 88.9% 92.8% -3.9% Northern Rail 82.1% 85.5% -3.4% Arriva Trains Wales 90.4% 93.5% -3.1%
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk