Friday 12 Mar 2010

EASTER RAIL UPGRADE FOR SOUTHAMPTON MAIN LINE

Region & Route:
Southern: Wessex
| Southern

A major programme of improvement work is due to take place on the railway between Southampton and Farnborough over the Easter weekend (Friday 2 to Monday 5 April) resulting in changes to the South West Trains timetable.

The work will focus primarily around two projects:

Basingstoke Signalling Upgrade
The third and final phase of a scheme to bring the signalling in the Basingstoke area into the 21st century is being carried out.  This will see equipment which was originally installed in the 1960s taken out and replaced with modern technology.  The upgrade will reduce the risk of problems occurring with the signalling, making train services more reliable for passengers.  This phase of the scheme covers the area between Basingstoke and Farnborough.

Freight Upgrade
As part of a £71m project designed to remove up to 50,000 lorries a year from the region’s roads and provide a cheaper, quicker and more practical way of transporting goods around the country, Network Rail is rebuilding three road bridges over the railway in the Winchester area.

Work has been taking place since 4 January 2010 to build a new bridge deck above the existing one at St Cross (B3335).  With the new part of the bridge nearing completion and the road due to reopen on 31 March, the old deck will be demolished over the Easter weekend.    The new, larger bridge will allow bigger 9' 6" or high-cube containers to be transported efficiently by rail from Associated British Ports' (ABP) Port of Southampton.

The tracks through two tunnels at Popham, Hampshire, will also be lowered at the same time as part of the scheme.

Both these major schemes can only be carried out when there are no trains running.  The work is being carried out at the same time over the Easter weekend in order to keep the amount of time that the line needs to be closed to the shortest time possible.  

Richard O’Brien, Network Rail’s route director for Wessex said: “Rail demand on this busy commuter route is significantly less at weekends and on public holidays than during the week, so the Easter weekend provides the best window to carry out this work so we can minimise disruption to passengers.  We thank the public for their patience while we carry out this important work.”

Craig Josey, Area Manager for South West Trains added: “We are working closely with Network Rail to keep disruption to a minimum and have plans in place to ensure that people can still travel over the Easter weekend.  We will keep our website updated with full information whilst work on these improvement schemes is being carried out”.

Notes to editors

A summary of the key timetable changes is detailed below:

Friday 2 April (Good Friday), Saturday 3 April and Monday 5 April (Easter Monday)
A reduced service will run across many parts of the South West Trains network.

Services from London Waterloo to Bournemouth/Weymouth

  • One train an hour will run between London Waterloo and Weymouth, diverted between Woking and Southampton Central to run via Guildford, Havant and Fareham.
  • Other train services on this route will only run south of Eastleigh.  Bus connections will run between Eastleigh, Winchester and Alton for trains to and from Woking and London Waterloo.
  • Replacement buses will also run between Woking and Basingstoke and Basingstoke and Eastleigh.
  • A reduced service will run between Guildford and Portsmouth to allow space on this route for the diverted Weymouth trains.

Services from London Waterloo to Salisbury and Exeter
  • Train services on this route will only run west of Basingstoke.
  • Replacement bus services will run between Basingstoke and Woking for trains to and from London Waterloo.

Services from London Waterloo to Basingstoke (stopping service)
  • Train services on this route will only run between London Waterloo and Woking.
  • Replacement bus services will run between Woking and Basingstoke.
  • Buses will also run to and from Woking for Farnborough and Fleet only.

Sunday 4 April (Easter Sunday)
A further amended timetable will run on Sunday 4 April:

Services from London Waterloo to Bournemouth/Weymouth
  • Trains between London Waterloo and Weymouth will be diverted between Woking and Southampton Central to run via Guildford, Havant and Fareham.
  • Other train services will only run south of Eastleigh.  Bus connections will run between Eastleigh, Winchester and Alton for trains to and from Woking and London Waterloo

Services from London Waterloo to Salisbury and Exeter
  • Train services on this route will only run west of Andover.
  • Replacement bus services will between Andover, Basingstoke and Woking for trains to and from London Waterloo.

Services from London Waterloo to Basingstoke (stopping service)
  • There will be no Basingstoke portion on the Alton train services
  • Replacement bus services will run between Woking and Basingstoke.

Advice for passengers
  • Check train times before travelling, either by visiting southwesttrains.co.uk or calling National Rail Enquiries on 08457 48 49 50.
  • Allow extra time for your journey (due to diversionary routes/replacement bus services).
  • If your journey includes a replacement bus service, please note cycles, prams and bulky luggage cannot be carried on buses due to limited space.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk