Easter line closure is platform for Livingston South redevelopment: Livingston South station platforms 1

Wednesday 28 Mar 2018

Easter line closure is platform for Livingston South redevelopment

Region & Route:
Scotland’s Railway: Scotland

Passengers who use the line between Edinburgh Waverley and Glasgow Central via Shotts are being reminded to plan ahead as the line will close for 10 days this Easter as part of a £160m project to electrify the route.

From 9pm Thursday March 29, to 6am Monday, April 9, no trains will run on the line while Network Rail engineers work to widen and extend both platforms at Livingston South and install and energise overhead line electrification (OHLE) at Midcalder Junction in a £2m package of Easter works.

The bulk of the work being delivered over Easter is to make sure the platforms at Livingston South station are safe and compliant for an electrified railway and long enough for the new six carriage trains that will be introduced on the route. 

As well as work to the platforms, the £3.5m redevelopment will see the construction of lifts on both sides of the station to deliver step-free access, installation of new staircases and the re-alignment of existing ramps.

Improvements to lighting and CCTV and enhancements to customer information systems, ticket machines, validators and waiting shelters will also be delivered at the West Lothian station.

The work is a key part of the Scottish government-funded investment to upgrade and electrify the line to improve reliability and enable the introduction of electric trains on the route by March 2019.

A bus replacement service will be in operation serving all stations on the route.

Brian Mallon, Network Rail programme manager for the Shotts Line Electrification project, said: “We know that closing the line is never a popular choice for passenger. The ten day closure is the best option to safely and efficiently deliver the work required and we have scheduled this work in such a way as to minimise disruption over the Easter holiday period when fewer people are travelling.

“Redeveloping Livingston South station is vital to the successful completion of the electrification project and the introduction of new faster, longer trains and we will also take the opportunity to do as much work as we possibly can all across the Shotts Line during the closure, to maximise progress and reduce the need for further disruption.

“We appreciate the cooperation of the local community and thank them for their patience as we deliver this massive investment to upgrade the railway.”

The closure has been carefully planned for the school holiday period, when passenger numbers are lower and some passengers may be able to be more flexible with their travel plans.

Passengers wishing to travel on these dates are being advised to allow longer time for journeys on replacement bus services. Those who wish to remain on the train are advised to use Livingston North on the Glasgow Queen Street line.

Information on alternative travel options can be found at scotrail.co.uk/LivingstonSouth and updates on the project are available via twitter @ShottsLineElec

Across Britain, more than 15,000 railway staff will be out delivering £118m-worth of investment at more than 400 locations as part of Network Rail’s long-term plan to create more reliable infrastructure and improved facilities for passengers.

Mark Carne, chief executive at Network Rail, said: “This Easter, thousands of rail workers will be working round the clock to deliver crucial upgrades to the rail network as part of the £50bn Railway Upgrade Plan.

“This huge investment programme will provide faster, better services and help relieve over-crowding to respond to the huge growth on Britain’s railways.

“While most of the network is open for business as usual, some routes are heavily affected and so we strongly advise passengers to plan ahead this Easter.”

A breakdown of how some journeys will be affected can be found by visiting nationalrail.co.uk/Easter and following #EasterBHWorks on Twitter.

 

Notes to Editors

Notes to Editors

No services will operate on the Edinburgh Waverley to Glasgow Central via Shotts route for a 10 day period over Easter. Busses will replace trains during this time. The line will be closed after the last service on the evening of Thursday, March 29. It will reopen for normal service on Monday, April 9.

Work will be delivered from the track to demolish platform 1 and reconstruct using a modular platform construction system. This will then be repeated on Platform 2

Platforms will be widened from 1.8m to 3m to create a safe station environment for the operation of electrified services.

Platform 1 (eastbound) will be extended 28m on the west side. Platform 2 (westbound) will be extended 28m split between the east and west sides. Both platforms will be circa 147m in length and extension will enable introduction of new longer trains that will operate on the route from 2019

A range of additional work as part of the wider electrification programme will be progressed during the 10 day line closure. This includes tie-in of new overhead line electrification (OHLE) system on the Shotts line with existing OHLE at Midcalder Junction.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk