‘East meets West’: rail project connects Oxford with Bletchley for first time in 50 years: Group Shot -8

Thursday 7 Mar 2024

‘East meets West’: rail project connects Oxford with Bletchley for first time in 50 years

Region & Route:
North West & Central: West Coast Mainline South
  • Major track milestone completed on Connection Stage One (CS1) of East West Rail project
  • Rail minister connects final section of rail at Steeple Claydon
  • Engineering landmark paves way for passenger services to start from 2025

The final section of track connecting Bicester and Bletchley has been laid today (Thursday 7 March) as part of the East West Rail (EWR) project to improve rail connectivity between Cambridge and Oxford. The project began by rebuilding Bletchley flyover, the first phase of the track work started in 2021. Since then 66 kilometres of new track has been laid. Passenger services are expected to start next year.

Once up and running, the new service will provide a fast sustainable transport option for local communities improving connectivity between Oxford, Milton Keynes, Bedford and Cambridge, reducing travel times and providing better access to jobs, healthcare and education.

The fully Government-funded programme is being delivered by the East West Rail Alliance (EWRA) which is a collaboration of four organisations including Network Rail, AtkinsRéalis, Laing O'Rourke and VolkerRail. Close collaboration with Network Rail’s Supply Chain Operations (SCO) team and supply chain partners has allowed EWRA to overcome challenges such as industrial action and national material shortages.

Key features of the first phase of the project have included:   

  • Use of a New Track Construction train (NTC) to install up to 85 per cent of track
  • 63 shifts completed with the NTC, one shift achieving  1.4km of new track in ten hours
  • Delivering all track materials via rail rather than lorries, reducing traffic and carbon emissions
  • 66,353 metres of track laid
  • 99,320 railway sleepers laid
  • 267,266 tonnes of ballast (railway stones) used
  • 18 switches and crossings (that help trains to switch tracks)
  • 427 rails delivered by Long Welded Rail Train (LWRT) totalling 216 metres in length

East West Rail Alliance is on track to hand over the project to Network Rail later in 2024, with remaining work this year including the installation of signalling, testing and the construction of Winslow station. Passenger services are due to start from 2025.

Rail Minister Huw Merriman said: “This is a significant milestone for one of the country’s most important rail projects and part of this Government’s plan to invest in rail infrastructure. 

“Having grown up in the area, I know just how much of a boost East West Rail will bring to local people. When complete, it will serve as a catalyst for economic growth in the region, bringing communities closer to job opportunities and education while making it easier to see friends and family.”

Eoin O’Neill, Capital Delivery Director, Network Rail, said: “The completion of the track construction is a major achievement for the EWR project as they move towards the commissioning of the new railway. The challenges faced by the EWR Alliance in reaching this project milestone were not insignificant. Strikes, ballast supply issues and large parts of the network being unavailable due to a viaduct closure all meant that original plans and commitments were made more difficult to achieve.

“Despite these challenges, the EWR Alliance team continuously adapted their plans and built a fantastic working relationship with our colleagues in Supply Chain Operations, and it was through this teamwork were able to deliver and overcome the challenges without affecting the infrastructure ready date. A lot of people talk about collaborative working but to me this is a tangible example of it working in practice to jointly deliver the programme.”

Mark Cuzner, EWR Alliance Director, said: “Joining the track east to west is clearly a hugely significant milestone for the project that has been achieved through the collaborative and innovative approach used by the project team. It is also a hugely symbolic moment as this is the first time the railway has been connected through this area in over 50 years. With the majority of our civil and track works now complete it signifies that we are entering the final stages of the project, with testing and commissioning already underway and the team on track to hand the project over to Network Rail later in 2024.”

Beth West, CEO, East West Railway Company, said: “This marks a significant milestone for our project and brings us another step closer to delivering a railway which will help people to access jobs, education and healthcare while making it easier to see family and friends, and travel for leisure.

“I’d like to thank everyone who has helped to build this part of East West Rail which will connect communities and improve everyday journeys as we look forward to passenger services starting on the first phase between Oxford and Bletchley from 2025, as planned.”                     

Notes to Editors

Video footage of the track construction is available here: https://youtu.be/R30G8OaYvqo

About East West Rail Alliance

The East West Rail Alliance was procured by Network Rail to construct the section of East West Rail between Bicester and Bletchley, and is made up of Network Rail, AtkinsRéalis, Laing O'Rourke and VolkerRail.

In May the Government announced a preferred route alignment between Bedford and Cambridge, including new stations which would serve Tempsford and Cambourne, and a southern approach to Cambridge.

About the East West Rail Project

The East West Rail Project is a once in a generation opportunity to connect people and businesses between Oxford, Milton Keynes, Bedford and Cambridge through a new direct rail line. It is a railway with community at its heart that will open up new journeys, cut travel times, and ease congestion on local roads. The route will connect people to the things and places that matter, bringing local benefit and sustainable growth by unlocking the social and economic potential of the area.

The East West Rail Project will be delivered in three Connection Stages: 

  • Connection Stage One: Oxford to Bletchley and Milton Keynes
  • Connection Stage Two: Oxford to Bedford
  • Connection Stage Three: Oxford to Cambridge

Network Rail was responsible for developing the first part of Connection Stage One, connecting Oxford with Bicester before the East West Rail Company (EWR Co.) was set up. Since 2018, EWR Co and Network Rail have partnered and are acting as the Department for Transport’s joint sponsors. 

EWR Co is now developing Connection Stage Two and Connection Stage Three to enable services to run to Cambridge via Bedford and plans to seek statutory powers under the Planning Act 2008, following a period of extensive consultation. 

About the East West Railway Company 

The East West Railway Company (EWR Co) is a non-departmental public body with limited company status set up by the Secretary of State for Transport in 2018 to deliver the East West Rail (EWR) Project.  

EWR Co aims to bring fresh thinking to the Project, challenging the industry status quo, leading to more efficient and cost-effective project delivery and better outcomes for the communities in and around the Project.

The corridor, which runs from Oxford through Milton Keynes and Bedford to Cambridge, is an economic artery that makes the UK a global leader in life sciences, technology and innovation, with the potential to create jobs, drive growth and attract investment for the entire country. EWR Co’s ambition is to unlock the full potential of this region that is vital to keeping the UK globally competitive in a way that considers the environment and offers value for taxpayers.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
0330 854 0100
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk