Planning consent received for East Linton station development: East Linton station

Tuesday 7 Sep 2021

Planning consent received for East Linton station development

Region & Route:
Scotland’s Railway: Scotland

East Lothian Council's planning committee has approved proposals which will see a station open in the village of East Linton for the first time in more than half a century.

The plans for East Linton will see the construction of a two-platform station on the East Coast mainline, with 126 car parking spaces. The station itself will be fully accessible with lifts and a footbridge connecting both platforms.

The planning application was submitted back in December 2020 following extensive engagement with the community – necessarily online due to COVID-19 restrictions – and local campaigners who have pushed for the return of the station for more than two decades.

The new station will support economic growth by providing a connection into Edinburgh Waverley, offering an excellent new link to public transport and enabling residents from the area to access and expanded range of employment, education and leisure opportunities.

It is generally the case that station projects act as a catalyst for further investment and economic development in local areas.  It is hoped that the construction of the new East Linton station will help support investment in the local community and further afield and will enhance and open-up transport links and improve connectivity.

Transport Minister Graeme Dey said:

“I welcome this announcement which is another significant step towards delivery of this important new station and will bring new travel opportunities to East Linton and the surrounding area.

“The Scottish Government has committed funding for this scheme which will have real potential to deliver a number of benefits for the local communities, including those who live in the village and commute into Edinburgh, and it will also help towards supporting our green recovery from the Covid-19 pandemic.”

Alex Hynes, managing director of Scotland’s Railway said: "We are delighted that East Lothian Council has agreed that this project can progress.  It is an exciting development that has the potential to transform the local community it will serve.

“Now that we have clarity on the planning decision, we will move to get onsite as quickly as possible and work with our partners to deliver this new station for our customers and the wider East Linton community."

 Councillor Norman Hampshire, East Lothian Council’s Environment spokesperson, said: “The approval of the East Linton Station planning application is a vital step towards the reopening of this station and I look forward to seeing the works progress rapidly.

“The Council is very supportive of the station project as it will deliver significant benefits to East Lothian by providing easy local access to the east coast mainline services. This will in turn make this area more attractive for inward investment which will support local communities and the economy.”

A station opened in the village of East Linton in 1846 but the last passenger services stopped in 1964.  

Notes to Editors

The plans for the new station at East Linton propose;

  • Two new 164m long, 4m wide station platforms and associated furniture (waiting shelters, seating and ticket machines).
  • A new footbridge will cross the railway, incorporating lift shafts and stairs on either side.
  • Lighting columns throughout the site and associated infrastructure/ equipment including CCTV
  • Car park, bus stop with shelter and a drop-off space.

The car park would provide an initial 126 parking spaces including blue badge priority parking and 18 electric vehicle charging. We will build in capacity to add further electric vehicle charging points when required.

Cycle storage facilities will be provided.

We are currently awaiting a final construction programme for the project and will announce an intended completion date for the project as soon as possible

Transport Scotland is working with the industry to discuss and agree a service/stopping pattern at the station.  This will be confirmed later in the year.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk