CUMNOCK DERAILMENT: Recovery works on track for Monday re-opening: derailed loco1

Friday 14 Aug 2015

CUMNOCK DERAILMENT: Recovery works on track for Monday re-opening

Region & Route:
Scotland’s Railway: Scotland

With the 16 derailed wagons and freight locomotive now removed from site, the recovery works at Logan, near Cumnock, are progressing to schedule.

The 130t engine was removed from the derailment site this afternoon, following the successful recovery of the 16 wagons over the course of Thursday.

Engineers have now begun to fully assess the track repairs required for the line to reopen.

Initial investigations have revealed significant track damage and engineers will work around-the-clock over the weekend to repair and replace rails, sleepers and other infrastructure.

A ScotRail Alliance spokesman said: “With extensive damage to the track and other infrastructure to be repaired, our engineers will be working hard throughout the weekend to reopen the line.

“The recovery operation is progressing to plan and we remain confident that we will be able to reopen the line for passengers on Monday, August 17.

“We understand the inconvenience this incident has caused and remain committed to restoring services as quickly as we can.”

Before lifting the engine and wagons, engineers had to first construct a 350m-long haul road, and operating pad, for the 1,000 ton crane required to remove or re-rail the wagons and locomotive.

The derailment occurred on Saturday, August 1, when two freight trains collided while delivering materials to an engineering work-site on the line, which was closed at the time. No-one was injured in the incident.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Nick King
Media relations manager (Scotland)
0141 555 4108 / 07515 617073
nick.king3@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk