Cumbernauld electrification works get underway

Region & Route:
Scotland’s Railway: Scotland

Engineers will begin work on the electrification of the Cumbernauld-Glasgow line this weekend (Sunday, June 23).

Following months of extensive preparatory work to the lineside and structures along the route, work to erect stanchions and string overhead power lines will take place between June 2013 and Spring 2014.

The £40m, government-funded, scheme will see over 50km of railway electrified as part of a wider £80m investment in the line between Cumbernauld and Scotland’s largest city.

As well as the main electrification works, the project will also be lengthening the Cumbernauld station platforms and constructing a turnback facility at Springburn.

The project marks the first phase of electrification on the Edinburgh-Glasgow Improvement Programme (EGIP), and the scheme will be delivered in time for the Commonwealth Games in 2014.

In order to complete these enhancements as quickly and efficiently as possible engineers will be working extensively at evenings and weekends with the following impact on services:

Gartcosh - Cumbernauld / Falkirk Grahamston and Motherwell – Cumbernauld

From Wednesday 26 June 2013 buses will replace trains from around 19:30hrs on Wednesdays and Thursdays.

Glasgow Queen St - Cumbernauld / Falkirk Grahamston

From Sunday 23 June 2013 buses will replace trains from around 19:30hrs on Sundays, Mondays and Tuesdays.

There will also have to be a number of all-day Sunday closures between Glasgow and Cumbernauld over the course of the project, with the first of these taking placeon Sunday, June 30 and Sunday, July 28.

A Network Rail spokesman said: “The project is a significant enhancement of the line between Glasgow and Cumbernauld and is the first step in a major transformation of the railway across the central belt.

“While we understand the inconvenience these work may cause some passengers, the project has been designed to deliver these enhancements in the most efficient, cost-effective and quickest way possible.”

A ScotRail spokeswoman said, “We’ve posted a revised train and bus timetable on our website, and organised on-train and station announcements to inform customers.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Scotland
0141 555 4109
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk