CONSULTATION ON ELECTRIFICATION STRATEGY LAUNCHED: Overhead line electrification (OLE)

Friday 15 May 2009

CONSULTATION ON ELECTRIFICATION STRATEGY LAUNCHED

Region & Route:
National

A formal consultation looking into expanding the electrified network was launched today as Network Rail, on behalf of the rail industry, published a proposed strategy on electrification.

The network route utilisation strategy on electrification, currently in draft form, forms part of a consultation on a long-term plan being developed by Network Rail in collaboration with industry partners to meet rising passenger and freight demand across the country. The electrification RUS outlines the benefits and value for money more electrification can bring, such as reducing the costs of running the railway, increasing capacity and lowering CO2 emissions.

Iain Coucher, Network Rail’s chief executive, said: "The consensus for expanding our electrified network is growing. The evidence outlined in this strategy sets out a positive case for a long-term commitment to electrification.

"Electric trains are not only better for the environment, but are quieter and smoother for passengers while causing less wear and tear to the track. They are more reliable and often faster. Further electrification will also help open up more diversionary routes so that we can keep people on trains and off buses as we carry out planned rail improvement work.

"Our plans to develop an engineering method that can install power lines quickly, and efficiently, without disrupting services and at a cost that is affordable are already at an advanced stage."

Compared to diesel traction, electric services have lower rolling stock operating costs, higher levels of train reliability and availability and lower leasing costs. The superior acceleration of electric trains can also help reduce journey times. Electric trains also provide more seats than diesel trains increasing capacity, while electric freight locomotives can haul longer trains.

Electrification can also play a role in reducing carbon emissions as well as improving air quality and reducing noise. Electric vehicles, on average, emit 20% to 30% fewer CO2 emissions than diesel.

Currently only 40% of the rail network is electrified, including most of the south east of England, and the main lines from London to Edinburgh and Glasgow, as well as the Merseyrail network around Liverpool and the Glasgow suburban network.

In the current economic climate, any investment will inevitably raise questions about affordability even where there are clear longer term cost savings, and the industry will need to work with government and other funders on this.

Were the funding secured for further electrification, the RUS recommends that the busiest 3,000miles of non-electrified routes should be electrified as a priority to achieve the greatest benefit. These routes include:

· The Midland Main Line, including services from London St Pancras to Sheffield

· Great Western Main Line covering services from London Paddington

· Strategic infill to provide more diversionary routes

The draft Network RUS: Electrification was drawn up by Network Rail on behalf of the rail industry, and received significant contributions from industry stakeholders including the Department for Transport (DfT), Transport Scotland, Welsh Assembly Government, Transport for London (TfL), The Passenger Transport Executive Group, Association of Train Operating Companies (ATOC) and Freight Operating Companies.

Network Rail will now carry out a formal 60 day consultation with industry partners and following consideration of any comments the strategy will be finalised and submitted to the Office of Rail Regulation to become an established strategy. In parallel, we will continue working with the Government as they assess the case for funding for a rolling programme of electrification.

More information about the RUS process can be found on the Network Rail website: www.networkrail.co.uk

Notes to editors

Operational benefits - Reduces rolling stock operating costs - Reduction in infrastructure operating costs (track wear and tear) - Increase in rolling stock availability - Passenger rolling stock replacement - Security of energy supply (oil price fluctuations) Passenger benefits: - Reduced journey times through quicker acceleration and shorter stopping distances, particularly for suburban services with frequent stops. ATOC estimates that journey time savings are in the region of a quarter of a minute for typical suburban services and half a minute for long distance services per station stop - Station ambience: electric trains create less noise, and don’t emit exhaust fumes - Reliability: electric trains generally have a lower failure rate than diesel equivalents, with electric trains twice as reliable (in miles per breakdown terms) - Reduction in rail replacement services (buses) – more diversionary routes will reduce the need to revert to buses - New journey opportunities: if electrification is combined with service recasts, it could potentially provide new through journey opportunities. - Additional seating capacity: on long distance high speed routes, where a diesel train with a separate power car would operate, electrification schemes eliminate the need for a diesel power car. As a result, electric trains on such routes generally provide additional passenger seating capacity within the same overall train length. For example, the two end vehicles of class 390 (Pendolino) trains contain a total of 64 seats. Capacity Benefits - In the case of freight services, the ability to haul greater trailing loads will reduce the number of freight paths needed freeing up capacity. - The superior performance of electric traction can provide significant journey time saving. Route Utilisation Strategies seek to balance capacity, passenger and freight demand, operational performance and cost, to address the requirements of funding bodies and stakeholders. Network Rail will take account of the recommendations outlined in a RUS when carrying out its activities to improve, maintain and manage the railway. In particular, the strategies will be used to inform the allocation of capacity on the network through application of the normal Network Code processes. Other than the Freight RUS, the Network RUS is the only RUS to cover the entire network. Owing to its scope, the Network RUS has been split up into a number of different strategies which are published separately. These include strategies for stations, rolling stock and depots and long distances and scenarios. The Network RUS process is being overseen by a stakeholder management group consisting of Network Rail, the Department for Transport, Transport Scotland, the Welsh Assembly Government, Transport for London, the PTE Group, ATOC, freight operating companies, Passenger Focus, London TravelWatch, RoSCos and the Rail Freight Group. The ORR attended stakeholder management group meetings as observers

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - National
020 3356 8700
mediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk