COMPLETED: North Downs Line between Guildford and Gatwick Airport reopened after signalling and level crossing upgrades: Guildford signalling centre

Sunday 28 Sep 2025

COMPLETED: North Downs Line between Guildford and Gatwick Airport reopened after signalling and level crossing upgrades

Region & Route:
Southern: Wessex
| Southern

Trains are running again on the North Downs Line between Guildford and Gatwick Airport following a two-week closure to complete major signalling and level crossing upgrades

During the closure, we upgraded four level crossings on the line; Chilworth, Tangley, Brook and Burrows Lane. All four crossings are now linked to the Guildford Area Signalling Centre, improving safety and reliability.  

At Brook and Burrows Lane level crossings, new radar technology scans the crossing before each train arrives, lowering the barriers only when the route is clear. 

At Chilworth and Tangley, new CCTV means a signaller can check the crossing and lower the barriers when it is safe. Burrows Lane, Tangley and Brook crossings are currently three of the "riskiest crossings" on the route and these works would decrease the risk of an incident by 97%.

Engineers also upgraded the signalling between Shalford and Gomshall. As part of these works, 16 signals were upgraded along this stretch of railway. Newer equipment means faults are less likely to occur, providing more reliable services for passengers.

Mark Goodall, Wessex route director for Network Rail, said: “We would like to thank passengers and lineside neighbours for their patience while we carried out these vital improvement works. Improving safety on the railway is our number one priority and these level crossing improvements have made giant strides in improving the safety of the line. Upgrading the signalling to bring it into the Guildford Area Signalling Centre will also streamline the railway and reduce the risk of faults on the line.”

The upgrades are part of a wider programme to modernise the North Downs Line, creating the capacity to run more services in the future.

Andy Gallaugher, GWR Station Manager for the North Downs line, said: "We’re grateful that train services are now running again between Guildford and Gatwick Airport.

“This work helps to lay the foundation for future capacity improvements on the line, helping even more people to access the airport sustainably.”

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Tom Moore
Communications Manager
Network Rail
07354531500
Thomas.Moore@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk