Changes to Chiltern journeys due to railway repairs and HS2 work: Aylesbury Culvert aerial with close up

Thursday 18 May 2023

Changes to Chiltern journeys due to railway repairs and HS2 work

Region & Route:
North West & Central
| North West & Central: Central

Passengers in Buckinghamshire are being advised to plan ahead as railway work later this year means major changes to journeys between August and October.

The first stage of work on the Chiltern Railways route will see Network Rail engineers making permanent repairs to a Victorian drainage culvert which passes underneath the railway in Aylesbury.

Faults found in the structure earlier this year* have since led to repeated short-notice closures of the line causing disruption for passengers.

To fix the issue once and for all, a 12-day railway closure is needed to repair the culvert between Monday 7 and Friday 18 August.

This will impact all trains between Aylesbury and Princes Risborough and Aylesbury Vale Parkway and Amersham.

To keep passengers on the move during this time, rail replacement buses will be in operation between:

  • Amersham – Great Missenden – Wendover – Stoke Mandeville – Aylesbury – Aylesbury Vale Parkway (for connections to London Underground)
  • Princes Risborough – Monks Risborough – Little Kimble – Aylesbury

Immediately after that from 19 August until 30 October, work will take place to allow the new high-speed, zero-carbon railway HS2, to pass under the existing railway**.

This will mean no train services for 10 weeks between between Aylesbury and Princes Risborough, with rail replacement buses laid on for passengers, between:

  • Princes Risborough – Monks Risborough – Little Kimble – Aylesbury

People are being being made aware of the work so they can plan their journeys in advance by checking www.nationalrail.co.uk

Denise Wetton, Network Rail’s Central route director, said: “We know there’s never a convenient time to close the railway and we’re sorry to passengers in Buckinghamshire who have already suffered from short-notice closures of the line between Princes Risborough and Aylesbury for several months.

“When completed, this vital work will mean more reliable journeys for passengers travelling between Aylesbury and Princes Risborough on a railway that’s fit for the future.”

Jacqueline Dey, Chiltern Railways' operators director, said:  "The damaged culvert has led to numerous short-notice cancellations this year, and we are pleased that a permanent fix will be in place before the end of the summer. Customers should be mindful that Network Rail and HS2 works will close the railway between Princes Risborough and Aylesbury for a further ten weeks after these repairs, with the line reopening again on Monday 30 October. Rail replacement buses will be in operation during this time, and customers should check before they travel.

"We know that this is a significant, long-term closure, but we are confident that the railway between Princes Risborough and Aylesbury will be more reliable as a result of these important works. We will be working with industry partners to keep residents informed before and throughout the closure, and thank customers for their patience while these works are completed."

Patrick Cawley, director for ‘On Network Works’ for Network Rail and HS2, said: “I’d like to thank passengers in Buckinghamshire for their patience this year while we carry out this vital phase of work between Aylesbury and Princes Risborough to prepare for the new high speed railway. HS2 will transform journeys between London, the Midlands and the North, providing zero-carbon journeys from day one and also making space on the existing railway network for more freight and local services.

“To help reduce disruption we’ve worked with our rail industry partners to combine closures needed for two major pieces of work on this route. We’re asking passengers to plan ahead and check before they travel at www.nationalrail.co.uk

Passengers are advised to check before they travel at www.chilternrailways.co.uk and www.nationalrail.co.uk or for updates and details of alternative travel arrangements during the extended closure.

Notes to Editors

*Network Rail will permanently repair the brick-built culvert which was damaged in March 2023, leading to repeated short-notice closures of the line.

A temporary repair was made, and monitoring equipment installed, but during heavy rain or repeated uses of the locks in the Grand Union Canal, the railway must close as water levels fill the culvert, obscuring the monitoring equipment.

This location is a rare example of where the railway wasn’t built first and the tracks were laid over the culvert which drains excess water from the canal basin.

Opening a lock can send many litres of water into the basin which, if it’s already full, must drain via the culvert.

**Network Rail and HS2 will work in partnership to move and replace more than a mile of track and signalling equipment between Princes Risborough and Aylesbury to make way for the new HS2 line which will pass beneath the existing railway.

The major work means there will be no train services between Aylesbury and Princes Risborough for a further 10 weeks with services resuming on Monday 30 October.

Chiltern Railways will operate a rail replacement bus service between Aylesbury and Princes Risborough during this time, calling at Little Kimble and Monks Risborough.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - North West & Central Region
07740 782954
NWCmediarelations@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk