Carstairs festive work to minimise passenger disruption: Carstairs Aerial from south

Tuesday 22 Nov 2022

Carstairs festive work to minimise passenger disruption

Region & Route:
Scotland’s Railway: Scotland

Network Rail will be working over both Christmas and New Year to deliver part of a key investment project to upgrade and remodel Carstairs Junction.

The activity is one of 560 projects and part of £90m of upgrade work being delivered across the UK network over the festive period when passenger trains are not running.

Working continuously from late evening on Christmas Eve through until the start of service on Tuesday, December 27 the team at Carstairs will install structures for signals, run overhead wires and remove redundant masts and equipment from across the project site.

The following week, the team will then work continuously from late on Hogmanay through until 13.00 on Monday January 2 to progress work on signalling, drainage and electrification equipment.

It is part of a phased programme of investment in the key junction on the West Coast Main Line which will simplify and upgrade the track-layout to clear an existing bottleneck on the network and enable the separation of non-stop passenger and freight trains from those stopping at the station.

Work delivered to date at Carstairs represents an investment of more than £100m in the junction to rationalise and simplify the track layout and modernise the signalling through one of the most critical sections of the Scottish rail network.

The installation of new sections of track and modern signalling will also speed up journeys between Glasgow and Edinburgh and will accommodate the longest freight trains on our network.

Extensive renewal and simplification of the layout was seen as the best long-term solution to deliver the reliable and resilient network needed at this key junction.

Jim McCleary, programme manager at Network Rail said: “Work over both Christmas and New Year will keep us on track with our preparations for the construction of the new track layout in 2023. This includes 10 kilometres of track and 27 new sets of switches and crossings, which allow trains to move between tracks.

“Access to the railway at this critical junction is very limited, but the team has worked hard with the wider industry to balance the needs of train operators with the longer-term benefits that will come from modernising the track, signalling and overhead line equipment.

“Working over the festive period helps us to protect the programme and deliver a significant volume of work at a time when trains are not running and with no disruption to passenger services.”

Notes to Editors

Carstairs junction sits 26 miles to the South-East of Glasgow on the West Coast Main Line. The triangular junction provides a route between Glasgow & Edinburgh and both Glasgow and Edinburgh to the south.

More than 200 services pass through the junction on an average midweek day with 12 train and freight operators regularly using the route.  The Caledonian Sleeper Lowlander service splits and joins in this location both morning and night for Glasgow and Edinburgh for Euston services.

Over the Christmas and New Year period the railway will be closed from Symington through to Lanark Junction on the West Coast Main line and to Auchengray on the Midcalder line to enable work.

Despite being largely restricted to Saturday nights, the project has already delivered more than 3km of track renewals and 1.5km of drainage, installed the new structures, and started the process of removing some of the redundant equipment.

Further phases of work in 2023 will see the addition of another 4km of new drainage, further embankment work and will complete the installation of 10km of new track to create a faster, more flexible and more easily maintained layout.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk