Carnoustie road closures for level crossing upgrade: Carnoustie level crossing

Thursday 7 Feb 2019

Carnoustie road closures for level crossing upgrade

Region & Route:
Scotland’s Railway: Scotland

Residents of Carnoustie are being reminded that the first of two road closures to enable work to upgrade the level crossing on the town’s Station Road will begin on Saturday night (Feb 9).

During the eight-day road closure, Network Rail engineers will begin work to renew the signalling system and infrastructure at the crossing adjacent to the town’s station in a £5.5m investment.

Work will include replacing the existing two long level crossing barriers with four barriers, enhancement of signalling equipment and complete renewal of the level crossing surface.

Due to the nature of the work, this upgrade can only be delivered by closing the crossing for two extended periods and putting road diversions in place.  

The level crossing will be closed to road traffic from the evening of Saturday, February 9, until the morning of Monday, February 18, and again from the evening of Saturday, March 9, until the morning of Monday, March 18.

The railway through Carnoustie will be closed each Sunday between February 10 and March 17.

Euan Falconer, Network Rail’s project manager for the upgrade, said:  We appreciate there will be disruption as a result of this work – particularly as there is a prolonged period where the road will be closed. However, this is the only way in which we can deliver the work required safely and efficiently.

“This work will further improve the safety of both road and rail safety and also enhance the reliability of the railway on the busy east coast main line. We are grateful for the patience of the local community while we carry out this important work.

Work at Carnoustie is part of a £9m package of enhancements that Network Rail engineers will deliver between Aberdeen and Dundee over six weekends in February and March – which also include track renewal and upgrades to the signalling system.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk