Passengers travelling on the south London lines into London Victoria can look forward to more reliable journeys after Network Rail delivered a bumper programme of upgrades over May and June. 

The work continues on Sunday 27 June with more works planned for later in the autumn and winter. It is being delivered as part of the Victoria phase 3 re-signalling project, a major project to upgrade 1980s signalling and key sections of track on the lines between London Victoria, Clapham Junction and Streatham. 

A packed programme of work over five recent weekends has seen the switches and crossings, the moveable track that allow train to change paths, at Balham North junction and Falcon Junction (Clapham) replaced with new, more reliable equipment.

Preparation work for the switch-on of the new signalling system and recontrol of the area to the state-of-the-art Three Bridge Rail Operating Centre made great progress with all key milestones for power and fibre cables, elevated cable routes, gantry foundation piles and signalling equipment cases met. 

Network Rail also used the closures over May to progress a major drainage renewal to prevent delays due to flooding in the Clapham Junction area.

Shaun King, Network Rail route director, Sussex, said: “We’d like to thank those passengers travelling over May for their patience while we worked to upgrade and modernise the infrastructure on this part of the network to give passengers better, more reliable journeys. Passengers will see immediate benefits from our work to improve drainage and track, with further improvements to come once the new signalling comes into use in 2023”.  

Chris Fowler, Customer Services Director for Southern, said: “On behalf of our current and returning passengers, we thank Network Rail for progressing these vital signalling and drainage upgrades right on schedule.

“This coming Sunday there will be no Southern trains between Victoria and East Croydon, so if you do need to travel, please check your route in advance. You can be assured we’re working hard with our railway partners to keep rail travel safe, while we build a better all-round experience for our customers.”

Following the Sunday 27 June closure, next line closures on the project will be Saturday 16 to Sunday 17 October, Saturday 27 to Sunday 28 November, and Saturday 25 December 2021 – Sunday 2 January 2022 (9-day closure).

Learn more at www.networkrail.co.uk/victoriaresignalling   

Work delivered over May in numbers:

Resignalling project

  • 21000 metres of power cable installation 
  • 4000 metres of fibre cable installation
  • 2000 metres - elevated cable route
  • 2 of 8 gantry piling foundations

Balham North junction

  • 6 point ends
  • New and improved junction layout
  • 349 yards of track renewed

Falcon junction (Clapham)

  • 4 point ends
  • New and improved junction layout
  • 248 yards of track renewed

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Leonard Bennett
Leonard.Bennett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk