BRIDGE SLIDE AT LANDMARK BLACKFRIARS PROJECT MARKS KEY MILESTONE IN NETWORK RAIL’S THAMESLINK PROGRAMME: Blackfriars Bridge Slide - Before

Monday 4 Jan 2010

BRIDGE SLIDE AT LANDMARK BLACKFRIARS PROJECT MARKS KEY MILESTONE IN NETWORK RAIL’S THAMESLINK PROGRAMME

Region & Route:
| Southern

The successful installation of a 350-tonne, 22-metre, concrete and steel section of bridge on the landmark Blackfriars station redevelopment over Christmas has marked a significant milestone in Network Rail’s £5.5bn Thameslink programme.

The new section of bridge was specially designed and built on six metre high trestles towers in a site compound to the east of the site, to keep the station open for as long as possible and to minimise impact on passengers. The strengthened bridge will now enable Network Rail to move the tracks from the west to the east side of the station for its future and revised track alignment, providing quicker and smoother journeys for passengers when the work in that area is completed and brought into use in late 2010.  Further improvements at Blackfriars, as part of the Thameslink programme, will also improve services for passengers by enabling significantly more passengers to travel to and through the capital by late 2011.

Taking 101 hours to complete by a team of 50, the precision engineering activity was meticulously planned. The total value of investment by Network Rail in the railway over the holiday period was nearly £100m, with £10m spent on Thameslink alone.

The main work at Blackfriars saw the existing, old bridge section carefully deconstructed and removed from its position between platform four and five at the north of the station by an 800-tonne mobile crane. Two hydraulic rams then slid into place the new section of bridge from the east side site compound.

Before the bridge slide could take place, Network Rail engineers needed to conduct important enabling work. This involved disconnecting the signalling, temporarily shifting communications cables running under the rail bridge from the west to the east, and removing track and ballast. All these elements were then reinstated and reconnected when the bridge slide was completed.

Lindsay Vamplew, Network Rail project director for Blackfriars, comments: “Sliding this 350-tonne bridge into place is a critical part of turning Blackfriars into a landmark of which London can be proud of.  This is an important milestone in the life of not just this project, but Network Rail’s Thameslink programme. Not only was the work highly complicated, but it was very challenging given the location and conditions.

“This project is important for the future vitality of London. We are pleased by the progress achieved and I would like to thank the dedicated team who worked long hours throughout the festive period to get the job done.”

Notes to editors

About the Blackfriars station redevelopment

· The redeveloped station will be the first to span the River Thames, with a new station built on the South Bank for the first time in 120 years, giving passengers direct access to key local attractions including the Globe Theatre and Tate Modern
· The north station will be completely redeveloped to create a spacious and airy entrance and concourse featuring improved interchange facilities with London Underground services
· The London Underground station will be significantly enhanced
· By the end of 2011 the station will be able to handle longer 12 car trains for the first time with significantly more trains stopping at the station every hour, meaning more seats and better journeys for passengers.

About the Thameslink Programme

· Network Rail’s £5.5bn congestion-busting Thameslink Programme will increase service capacity and frequency on one of London’s busiest and fastest growing passenger routes
· Will upgrade a crucial railway artery running through London from St Pancras in the north, to Blackfriars and London Bridge in the south
· It will significantly increase the number of rail services between Brighton and Bedford, delivering benefits for passengers and the UK economy
· Reduce pressure on key London Underground services by expanding the Thameslink network to include extra stations, allowing trains to travel direct to more destinations (e.g. Cambridge to Gatwick direct)
· Major reconstruction at three key stations (Blackfriars, Farringdon and London Bridge) will improve the passenger environment and act as a catalyst for regeneration in some of London’s most deprived areas.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk