Breaking ground at new Leven station site: Alex Hynes at Leven

Monday 27 Feb 2023

Breaking ground at new Leven station site

Region & Route:
Scotland’s Railway: Scotland

Work is now under way to build the new Leven station as part of the £116m Scottish Government funded Levenmouth Rail Link project.

Leven will be one of two new stations built on the route, alongside Cameron Bridge, reconnecting communities in Levenmouth to the rail network for the first time in over 50 years.

The station will boast 205m island platforms and a pebble styled pavilion area as the entrance to the new station.

Located next to Leven Leisure centre, with easy access to connecting bus services and all existing active travel routes, the new station will have 133 car parking spaces with provision for EV charging and cycle storage. There will also be ‘blue badge’ accessible parking spaces.

Work on the new station began on with the construction of the foundations for the platforms. This will be done using more than 98 precast units and around 200 cubic metres of concrete.

It is anticipated that work to create the new station will take approximately 14 months and it will be opened as part of the overall Levenmouth Rail Link in spring 2024.

Alex Hynes, managing director of Scotland’s Railway said: “I am delighted to be here to see work begin to construct the new Leven station.

“Leven and Cameron Bridge stations will be the gateway to the rail network for local people and it is great to see work getting moving on what will be the public gateways of the project.

“This new line will also serve other areas of Fife and allow the community better connectivity which means increased access to employment, education and make it easier for people to visit this beautiful part of the Fife coast. The benefits this brings are countless.

“In the coming months, the community will see a lot of work happening and quickly as the project gathers momentum and starts to build towards the opening of the line in spring 2024.”

A planning application for the new Leven station was submitted in early October and a combination of permitted development rights and ‘prior approval’ enables the project to progress work within the confines of the railway corridor. Planning permission is still being considered by Fife Council for wider elements of the station design.

Following successful completion of a range of preparatory activities, the project to deliver the new Levenmouth Rail Link kicked off in March 2022.

Work includes:

  • 19 single track kilometres of new / reinstated railway. (Fully double tracked railway)
  • Two new modern accessible stations
  • Electrification of the line
  • Work with partners to optimise interchange options connecting stations.

Notes to Editors

Current Status:  

The project has completed the first mile of track, which has now been commissioned and being used to support construction of the subsequent phases of work on the project

Current work to the west of the route includes fencing, re-profiling of embankments, drainage and cabling and track works on the 2nd mile section.  Bridge works are ongoing along the length of the rail corridor. 

  • Diversion of utilities has started on the Leven Bridge and it is anticipated that preparatory work on the (Bawbee) Leven bridge will get under way shortly.
  • Work has commenced at Cameron Bridge station.
  • Planning applications for both station developments on the line were submitted to Fife Council in October 2022.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk