Bexleyheath line welcomes passengers back after £6.6 million investment over 9 days: Engineering works

Monday 24 Feb 2020

Bexleyheath line welcomes passengers back after £6.6 million investment over 9 days

Region & Route:
Southern

Kent passengers are seeing the benefits today as Network Rail handed the railway back on time following a 9-day closure for vital engineering work to protect passengers from disruption caused by landslips.

More than 200 engineers worked around the clock at 17 sites to protect the railway between Kidbrooke and Barnehurst. Over the extended closure, they have carried out the lion’s share of the £6.6 million improvement programme to this stretch of railway.

After four landslips in the last decade, Network Rail closed the line over the half term as part of a major project to protect passengers from further disruption.

The work involved removing 2,500 tonnes of mud and trees so engineers could reduce the steepness of the cutting slopes, which are prone to landslips during long periods of wet weather.

Engineers also brought in another 8,000 tonnes of material, such as gravel and concrete and built retaining walls along both sides of the cutting, stretching 650 metres. The walls are made from steel beams, driven into the ground and then finished with concrete blocks to stop any future landslips from reaching the tracks.

Fiona Taylor, Network Rail route director, Kent, said: “I’d like to say thank you to the passengers who have had their journey’s disrupted whilst we carried out these major resilience and improvement works. 

“We know there is never a good time to close the railway, so we worked during the February half-term when passenger demand is typically lower.

“The work we have carried out will significantly improve the reliability and performance of the network, giving passengers the level of service they deserve.”

David Statham, Managing Director, Southeastern, said: “Above all, our passengers on the Bexleyheath line through Barnehurst want a safe and reliable service, and so I’m pleased that this vital work undertaken by Network Rail will protect this stretch of track for the future.”

Highlights of the engineering work completed include:

  • Deep cleaning of the stations, painting of booking halls and platform furniture, toilet facility improvements and clearing vegetation.
  • Track maintenance to improve reliabilty and provide smoother rides from Blackheath Junction to Falconwood station.
  • Refurbishment of Perry Street Fork Junction, where the Bexleyheath line meets the Greenwich line, to prevent faults and reduce delays.
  • Signalling and power supply resilience work, including the replacement of electrical equipment to prevent future power and signalling failures.
  • Canopy, platform and drainage improvements at Barnehurst, Bexleyheath, Welling, Falconwood, Eltham and Kidbrooke stations.
  • Vegetation management and drainage clearance along the Bexleyheath line.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Leonard Bennett
Leonard.Bennett@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk