Bedfordshire passengers urged to plan ahead as Midland Main Line Upgrade continues: An example of swtiches and crossings

Tuesday 7 May 2019

Bedfordshire passengers urged to plan ahead as Midland Main Line Upgrade continues

Region & Route:
Eastern

Network Rail is urging passengers in Bedfordshire to plan ahead as the latest stage of the Midland Main Line Upgrade takes place this weekend.

On Saturday, 11 and Sunday, 12 May, Network Rail engineers will install four new sets of points, the specialist piece of equipment which allows trains to move from one piece of track to another, at Sharnbrook Junction, which is on the line between Kettering and Bedford.

The work is vital in the construction of a new line between Bedford and Kettering, which will enable more services to run, specifically providing the capacity to run six trains per hour to London St Pancras by the end of 2020, up from the current five per hour.

To allow the work to be carried out safely, no trains will be able to run on the line between Bedford and Corby and services will be affected in the following way:

  • Trains will start/terminate at Corby
  • Trains will not operate between Wellingborough and Bedford
  • Rail replacement buses will operate between Corby, Wellingborough and Bedford
  • Trains will operate between Bedford and London St Pancras International but will not call at Luton or Luton Airport Parkway
  • Journey times will be significantly extended

Rob McIntosh, Route Managing Director for Network Rail, said: “I would urge all passengers planning to travel between Bedford and Corby this weekend to plan ahead and check before they travel as work takes place as part of the Midland Main Line Upgrade.

“This work is really important and is the latest stage of work to construct a fourth rail line between Bedford and Kettering which will provide the capacity for more services to run. This will enable us to continue to railway which meets the needs of the passengers, communities and economies we serve.

“There’s never a good time to work on the railway, we do so at the weekend as it is a time when fewer people travel, but we do understand it can still cause disruption and we do apologise for this.”

Jake Kelly, Managing Director for East Midlands Trains said: “As the Midland Main Line Upgrade work continues, we are advising any passengers travelling to Bedford and Corby on the 11th and 12th May to check before they travel as their journeys will be disrupted.

“We apologise for any inconvenience caused by the disruption during this time.”

ENDS

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Amy Brenndorfer
Senior Communications Manager
07858375508
07730359569
Amy.Brenndorfer@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk