Tuesday 24 Jan 2023
Beaulieu Park station contract awarded to J Murphy & Sons Ltd
- Region & Route:
- Eastern: Anglia
Network Rail has awarded the first of two contracts to build the new railway station for Chelmsford’s Beaulieu development to J Murphy & Sons Ltd.
The £37.8m contract includes work to begin construction and enabling work for the new station on behalf of partners Essex County Council and Chelmsford City Council. This phase of the work includes set up of site welfare, earthworks, civils, modifications to track and signalling systems to facilitate the main construction phase of the new facility.
Main construction for the new station facility will be part of a second contract expected to be awarded in the coming months to complete the station and open it to train services for the benefit of passengers.
As part of a wider regeneration scheme, the new station has been designed to support the wider economic development of the area and its construction will include:
- Three platforms with a central loop line and new tracks to enable stopping services to call at the station while allowing fast trains to pass through unimpeded
- Step free access to all platforms via 2 lifts
- Accessible toilets, baby change facilities, waiting area and space for retail/catering
- Ticketing facilities, with ticket vending machines and a gate line
- Pedestrian and cycle access routes to the station
- 500 spaces for cycle parking and storage
- A bus interchange including bus stands for local services
- Pick up and drop off area with dedicated taxi bays
- Parking for over 700 cars, 5% of which to be designated Blue Badge bays, and motorcycle spaces, as well as dedicated parking for station staff, emergency services, and a dedicated space for service access
J Murphy & Sons Ltd have already been working on the project by finalising the design for Beaulieu Park station and have begun to establish the site compound to undertake the early enabling works.
The main construction phase will start later this year and the new station is currently expected to be completed and open by the end of 2025. Once open, the station will be managed by Greater Anglia and served by its fleet of new trains with services into London.
Katie Frost, Network Rail’s route director for Anglia, said: “Beaulieu Park is an excellent example of what the railway industry can do when working in partnership with local organisations to improve the railway for the benefit of communities and businesses. This is a great opportunity to show how we can work collaboratively with all our partners to begin to deliver the new station for the Beaulieu community.”
Al Pattison, Operations Director, J. Murphy and Sons Ltd, said: “We are excited to begin building this new station for the people of Beaulieu. The station has been developed by our teams for the last three years and is now ready for delivery. Murphy have previously demonstrated our expertise on the building of Soham Station, which we completed ahead of schedule. The team is looking forward to getting started on site and continuing our partnership with Network Rail.”
Cllr Lesley Wagland OBE, Essex County Council Cabinet member for Economic Renewal, Infrastructure and Planning, said: “The appointment of J Murphy and Sons to construct Beaulieu Park train station is another significant step towards starting the development of this exciting and important project, which will play a significant role in allowing Essex County Council to future proof transport services in the area and support wider economic growth.”
Cllr Stephen Robinson, Leader of Chelmsford City Council, said: “The new station is an important part of the extensive and vital infrastructure being put in place to support the new Chelmsford Garden Community. It will reduce the need to drive into central Chelmsford and tackle congestion, by encouraging greener options like cycling, walking and public transport.”
SELEP Chair, Sarah Dance, said: “As a key funder of Beaulieu Park Railway Station, SELEP is delighted to see this important project progress to its next phase of development. Centred in a key growth area for the City of Chelmsford, Beaulieu Park Station will provide a sustainable transport hub for the north Chelmsford growth area, which will provide new homes and modern office and business space to the north east of Chelmsford. This will offer improved access to the rail network for local residents but also the wider area of Maldon, Braintree and Uttlesford districts, whilst removing pressure from Chelmsford City Centre.”
Martin Leach, Managing Director, Strategic Land and Major Projects, Countryside, said: “We are delighted to have reached the next milestone of this major project, which will bring such a crucial piece of infrastructure to the area. For a long time Countryside (now part of the Vistry Group) along with our development partner L&Q have been working in partnership with Essex County Council, Chelmsford City Council and Network Rail, to bring this brand-new railway station to fruition. Once open, the station will significantly improve transport connections for Beaulieu residents and the wider Chelmsford community. We look forward to seeing the construction of the station progress in the coming months.”
Adam Simpson, Director of Project Management and Development at L&Q, said: “We are very excited to be progressing with the growth of this new community in the heart of Essex and the Beaulieu Station forms an integral part of that. We welcome the continued support and partnership work with Chelmsford City Council, Essex County Council and Network Rail, as well as Countryside, our delivery partners at Beaulieu, and look forward to having our Beaulieu residents riding the first train from their new local station.”
For more information about the Beaulieu Park station project please visit our project webpage: www.networkrail.co.uk/beaulieu
Follow us on Twitter @networkrailANG using the hashtag #BeaulieuParkStation
Notes to Editors
Notes to Editors:
- Essex County Council, in partnership with Chelmsford City Council, successfully secured £218m of funding from the Government’s Housing and Infrastructure (HIF) fund together with £34m contributions from the South East Local Enterprise Partnership and the developers of Beaulieu, Countryside and L&Q.
- On 15 December 2022, Network Rail entered into a contract with Essex County Council to deliver Beaulieu Park station. Read more here: Work to begin on much awaited Beaulieu Park Station - Essex County Council
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Network Rail Anglia Press Desk - Stephen Deaville
Senior Communications Manager
Network Rail
0330 8577 132
AngliaPressDesk@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk