Bawbee Bridge re-opens earlier than planned: bawbee bridge opens3

Friday 1 Dec 2023

Bawbee Bridge re-opens earlier than planned

Region & Route:
Scotland’s Railway: Scotland

The new Bawbee bridge officially opened to traffic on Tuesday (28 November), earlier than had been planned.

Work to replace the structure, which was weight-restricted and at the end of its lifespan, was funded by Fife Council and delivered by Network Rail as part of the wider Levenmouth Rail Link project.

During the demolition of the original bridge, a temporary road bridge was in place to carry around 18,000 vehicle movements per day and minimise disruption.

With the new Bawbee bridge in place, the temporary road bridge will be removed and work will continue to create the car park for the new Leven station.

It’s a significant piece of work, with the new structure boasts 7,000 tonnes of stone and 100 tonnes of steel reinforcement.

Sean Clemie, project manager for the bridge works, said: “It’s fantastic to see the new Bawbee bridge open and to see vehicles cross the new structure.

“Bridge demolitions in themselves are often straight forward enough, but most carry numerous utilities over railways and rivers. The challenge is to deliver a programme to have services diverted to a temporary structure and then reconnected over the permanent structure. This is what takes the time.

“Getting this structure over the line is a huge milestone and it allows us to progress with the station carpark and to aim to get everything ready for the opening of the new rail link next year.”

Councillor Colin Davidson, of Fife Council's Levenmouth Area Committee, said: “I am delighted to see the Bawbee Bridge open to traffic and especially delighted that the contractors were able to really push ahead and open it ahead of schedule. “

“The new bridge is looking fantastic, and I’m pleased to see we have kept some of the original bridge in there with the internal stonework.

“This is a significant improvement to our local road network and I want to thank the local residents and business community for all their patience. It has been a challenging and complex project, but one which will undoubtably benefit the area going forward.”

Construction of the bridge saw sixteen 18m-long reinforced concrete beams and 18 precast concrete parapets, each weighing 7.5 tonnes craned into place. In addition, 770 cubic metres of concrete was also poured as part of work to create the bridge.

Sandstone from the original structure has been used on the new bridge to create the internal facings.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Eddie Harbinson
Media Manager
Network Rail
edward.harbinson@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk