Aberdeen-Inverurie double-tracking begins this weekend: NR EasterWeekend Day1 15

Thursday 2 May 2019

Aberdeen-Inverurie double-tracking begins this weekend

Region & Route:
Scotland’s Railway: Scotland

Passengers are being reminded that Network Rail engineers will be working from this Saturday (May 4) until mid-August to complete a multi-million-pound upgrade to track and signalling between Aberdeen and Inverurie.

From May 4 to August 19, the railway will undergo a series of closures to allow engineers to double the track between Dyce and Inverurie, carry-out bridge upgrades and deliver signalling enhancements.

The 15-week programme is part of the Scottish Government-funded Aberdeen-Inverness Improvement Project.
The following service alterations will be in place during the upgrade works:

          May 4–June 14: Buses replace trains between Dyce and Inverurie.

          June 15–August 9: Buses replace trains between Dyce and Huntly.

          August 10–August 12: Bus replace trains between Aberdeen and Inverness

         August 13–August 19: Buses replace trains between Aberdeen and Huntly.

Over the 15 weeks, engineers will lay 10 miles of rail over nearly 40,000 sleepers and replace or refurbish 19 bridges on the line.

The work builds on the closure of the line between May and August 2018 which saw the successful completion of the first phase of double-tracking between Aberdeen and Dyce.

The Aberdeen-Inverness Improvement Project will increase capacity on the route improving services into the two cities.

The benefits of the project for ScotRail customers include:

         More services between Elgin and Inverness (from December 2018), increasing during 2019 until there is an hourly             service all day, providing 1,300 additional seats.

         A half-hourly service all day between Inverurie and Aberdeen during 2020, with extra services at peak times,                       providing 3,000 additional seats each day

         Additional Elgin-Aberdeen early morning and late evening services.

         InterCity trains operating between Aberdeen and Inverness, providing an extra 1,400 each day between the two               cities.

         A new direct service between Inverurie and Montrose, reducing the need to change in Aberdeen.

Billy McKay, Network Rail senior programme manager, said: “Double-tracking the line between Aberdeen and Inverurie will improve reliability on the route and allow a significant increase in the number of services available to customers.

“The Aberdeen-Inverness Improvement Project means more services and more seats for passengers and our engineers will be working around-the-clock to complete this complex programme as quickly as possible.

“We understand the inconvenience the work will cause to some passengers and residents, but such a huge engineering project cannot be delivered without the closure of the line. We are encouraging customers to leave extra time for travel, and plan journeys in advance.”

Derek Glasgow, ScotRail Aberdeen-Inverness project manager, said: “This is a significant project that will play a critical role in delivering a better service for our customers, as we continue to invest in Scotland’s Railway.

“We know that this level of engineering works will be an inconvenience, but we will do everything we can to keep customers moving with replacement bus services in place for the duration of the line closures.”

More information is available at ScotRail/A2I/Timetable as well as on the ScotRail app.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk