Aberdeen-Inverness rail closure enables station works: Inverness Airport Masonry bridge

Wednesday 6 Jul 2022

Aberdeen-Inverness rail closure enables station works

Region & Route:
Scotland’s Railway: Scotland

Passengers are being reminded that services between Aberdeen and Inverness will be disrupted this weekend as work to build the new Inverness Airport station continues.

Network Rail will carry out 54 hours of continuous working from Friday night until Monday morning to carry out work on the station development that cannot be undertaken safely while the railway is open.

Bus replacements will be in place between Inverness and Nairn and Inverness and Elgin on Saturday and between Inverness and Nairn on Sunday. Passengers should check before they travel and plan their journey at www.scotrail.co.uk

Since starting work last October the new £14m station at Inverness Airport has seen the construction of new platforms, the creation of the foundations for what will form the footbridge and lifts and the start of work to create the access road and car park at the site adjacent to the airport.

This weekend will see the demolition of the masonry road bridge to the east of the station site, installation of drainage, platform works and welding and stressing of the double-track section which has been created through the station.

The project, which is scheduled to complete in December, will deliver a two-platform station on the Aberdeen-Inverness line with step-free access, via a footbridge with lifts.  

The station will have 64 car parking spaces with 10 electric charging facilities, four disabled spaces and cycle parking. There will be a new access road to the station for motorists and access to both platforms for pedestrians and cyclists.

Inverness Airport station will deliver improved travel links to the growing Inverness Airport Business Park and the new town of Tornagrain.

David Millar, Project Manager for Network Rail said: “The construction of Inverness Airport Station continues to gather momentum and this weekend marks a significant point in the project. The removal of the old masonry arch bridge and connecting the passing loop are both important milestones in the delivery of the new station.

“We apologise for any inconvenience while the line is closed this weekend both to those intending to travel and to anyone who lives close to the site where we will be working continuously from Friday night until Monday morning.

“We appreciate your patience while we deliver this important addition to the area’s transport infrastructure.”

Notes to Editors

Notes to editors

Details of alternative travel options during the weekend closure covering Saturday, July 9, 2022 to Sunday, July 10, 2022 are detailed below.

Engineering work is taking place between Inverness and Aberdeen, closing some lines.

Saturday:

  • Services between Inverness and Elgin will be cancelled and replaced by a bus throughout.
  • Services between Inverness and Aberdeen will be cancelled and replaced by a bus between Inverness and Nairn.
  • The 04:56 Inverness to Edinburgh service (via Aberdeen) will start at Aberdeen at 07:08.

 Sunday:

  • Services between Inverness and Aberdeen will be cancelled and replaced by a bus between Inverness and Nairn.

Planned Work

Work at the site of the new station will to be carried out within the 54hr possession (line closure) 00:10 Sat 9th July to 04:45 Mon 11th July – This means that work on site will be continuous from Friday night until Monday morning

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk