A71 in West Calder to re-open early: Work on track at West Calder to re-open bridge two weeks ahead of schedule

Monday 3 Apr 2017

A71 in West Calder to re-open early

Region & Route:
Scotland’s Railway: Scotland

Network Rail has announced that the A71 in West Calder will re-open with temporary traffic lights in place more than two weeks ahead of schedule following the reconstruction of the bridge over the railway in the town.

The structure, demolished over the weekend of 7/8 January,  was reconstructed as part of a challenging 16 week programme which has delivered the re-opening of the road, 15 days earlier than planned on 10th April 2017.  The team will then work to complete the bridge, remove temporary traffic light controls and fully re-open the A71 by 16 May.

Though the demolition of the bridge was required due to the age and condition of the structure, the project itself was part of wider work on the Shotts line ahead of the electrification of the route by 2019 as part of a Scottish Government investment which is being delivered by Network Rail Infrastructure Projects.

The bridge reconstruction involved 37 lifts using a 750 tonne crane - the heaviest of which was the 67 tonne parapet unit as well as the installation of 24 x 18m long piles to support the construction of the north abutment of the bridge.   The project also used 15000 tonnes of material to create the compound and access road and 400 cubic metres of concrete to construct the new bridge.

A stronger bridge deck has been put in place and higher parapets (side walls) have been installed to comply with safety legislation on structures over an electrified railway.

Mak Kader, Network Rail’s programme manager for the Shotts Line Electrification, said: “We are delighted that the work in West Calder has gone so well.

“Our primary concern throughout this time has been the impact of the road closure on the local community and it is very welcome news that the road is re-opening ahead of schedule. 

“Given the location, this project was always a huge logistical challenge but with the scale and complexity of what has been delivered it is credit to the Network Rail project team and contractor Bam Nuttall for expediting works. While the road re-opening early is excellent news, we will maintain our focus until work is complete and the road fully re-opens

“We understand the impact that the unavoidable closure of the A71 had for road users, businesses in the town, and those communities adjacent to the diversion route, however, this has proven to be the best way to minimise disruption for the community.

“We thank everyone inconvenienced by this work for their patience and cooperation.”

Network Rail worked with West Lothian Council to put in place an appropriate ‘all vehicle’ diversion and delivered work at a number of locations to enhance roads in the area ahead of the increased volumes of traffic expected during the A71 closure.

In addition to the diversion route, other safety measures such as speed limits, parking restrictions and temporary traffic lights were put in place to help to maintain the flow of traffic from the diverted A71 route.

 

Construction facts

 15,000tonnes of material used to create access road and site compound

500 and 750 tonne cranes used in the construction

Bridge mainframe consists of 37 pre-cast concrete units

Heaviest single unit was a 67tonne parapet section

Bridge span has been widened from 11.8m to 13.7m

Bridge height over railway has been increased from 4.42 to 4.69m above the track

 

 

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - Owen Campbell
NR Press Office 0141 555 4108 / 07515 617073
Owen.Campbell1@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk