Over four consecutive November days, engineers will be replacing 50-year-old track in platforms 2 and 3 at Lowestoft station to help drive down delays for Suffolk and Norfolk rail passengers.
Currently, the ground beneath the rails is saturated in several places along the platforms, affecting the condition of the track and increasing the likelihood of faults that can cause disruption. Oil from previous generations of trains is also visible, leading to an unsightly appearance and contributing to the deterioration of the track bed.
Railway engineers will be using a specialist vacuum machine to remove areas of old ballast – the stones that support the track – before replacing it with fresh material. Sleepers and rails will also be replaced at various locations within the platforms. This work will help to keep passengers moving safely, smoothly and reliably into the future. Lowestoft is a crucial point on the local rail network, with direct connections to both Norwich and Ipswich, so minimising issues here supports punctual journeys right across the region.
The work will take place between Friday 13 – Monday 16 November inclusive, with train services affected on both the Lowestoft-Norwich and Lowestoft-Ipswich lines as follows:
Buses replace trains between:
- Lowestoft and Norwich
- Lowestoft and Oulton Broad South
- Lowestoft and Haddiscoe (Friday and Monday only)
- Reedham and Lingwood via Cantley
Trains will continue to operate between Ipswich and Oulton Broad South, and between Norwich and Great Yarmouth.
Passengers should check before they travel at greateranglia.co.uk
Joe Kennedy, Infrastructure Director working as part of GBR Anglia, said: “The vital work we’re doing in November will help us provide the best possible service on these busy and important routes for years to come. We’re really sorry for the disruption, especially on the two weekdays, but this is a big job that we must get done to maintain a reliable railway.”
GBR Anglia brings c2c, Greater Anglia and Network Rail Anglia together under a single unified structure on the journey to Great British Railways. The three organisations are increasingly planning and delivering as one railway, enabling faster and more joined up decision-making.
Contact information
Passengers / community members
Network Rail national helpline
03457 11 41 41
Latest travel advice
Please visit National Rail Enquiries
Journalists
Richard Cooper
Communications manager
Network Rail
0330 8577 132
richard.cooper3@networkrail.co.uk
About Network Rail
We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.
Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.
Follow us on Twitter: @networkrail
Visit our online newsroom: www.networkrailmediacentre.co.uk