30-YEAR KENT RAIL STRATEGY PUBLISHED: Southeastern service

Friday 22 Jan 2010

30-YEAR KENT RAIL STRATEGY PUBLISHED

Region & Route:
| Southern

Network Rail has published the final version of the Route Utilisation Strategy (RUS) for Kent, which sets out a 30-year vision to create a bigger and better railway to serve Kent, parts of East Sussex and south London.

Longer and faster trains, more journey options into London, better access to stations and improved reliability are all recommended outputs to meet future passenger needs.

Dave Ward, Network Rail’s route director for Kent, said: “Owing to the high number of trains already running across Kent and East Sussex, there are very few options to run additional services into the capital. However, there are opportunities to run longer trains across these routes which will result in extra seats and reduced congestion for passengers.  Kent will become the best connected region in the country to London stations, with services to seven out of the 11 main stations.  

“There is no doubt we face many challenges in order to enhance the railway in the coming years, but through a robust strategy, we aim to improve journeys in one way or another for as many people as possible.”

The RUS identifies meeting rising demand as a key challenge for the railway in Kent.  Based on 2008 figures, total passenger demand is forecast to grow faster than elsewhere on the rail network, with 30% more passengers by 2022. The launch of Southeastern’s high speed service between Kent and London St Pancras in December 2009 has already provided some much needed extra capacity, reduced journey times considerably and brings the most significant opportunities to further enhance the region’s railway.

Another major scheme set to reshape rail travel through Kent to the capital is the Thameslink programme.  This project includes substantial rebuilding and re-modelling of Blackfriars and London Bridge stations, providing more journey options, as well as making provision for up to 24 trains per hour through London, benefiting hundreds of thousands of rail passengers daily. 

Trains operating from the Tonbridge area into Cannon Street are expected to be incorporated into the Thameslink network, calling at London Bridge and onwards to Blackfriars, Farringdon, St Pancras International and further north.   It is also likely that services operating on the Maidstone East line will operate through the Thameslink network via Bromley South, again providing new journey opportunities for passengers as well as providing higher capacity trains. 

The Thameslink programme will also trigger extensive timetable improvements across much of Kent, Sussex and south London in order to make the best use of limited capacity.

The Kent RUS was published as a draft for consultation in April 2009 and received some 86 formal responses from stakeholders which have been extremely valuable. Significant feedback was received, for example, regarding the envisaged withdrawal of direct services between Hastings and London Cannon Street and in response the RUS appraises options for those likely to be impacted. As a result, the RUS recommends that all trains on the Hastings line to London Charing Cross call at London Bridge for access to the City and at peak times are also formed of slow and fast portions between Hastings and Tunbridge Wells in order to offer reduced journey times.

The Kent RUS has been led by Network Rail, but developed by the whole industry.  It analyses current demands and predicts future trends in order to make recommendations for improving the railway for as many people as possible.  Passenger and freight train operating companies, the Department for Transport and travel watchdog, Passenger Focus, have all been involved in the preparation of this document. 

In addition to capacity improvement schemes, the RUS also makes recommendations to improve Kent’s stations.  While a number have already been identified for improvements under the government’s national stations improvement programme and Access for All schemes, the RUS also outlines plans to provide more car parking spaces at stations across the county. 

Other areas examined in the RUS include increased line speeds, improved connectivity across the region, an allowance for the predicted increase in freight traffic and enhancements to the infrastructure to improve reliability.

Notes to editors

1.    Although the High Speed 1 line is not included within Network Rail’s license, it would not be possible to develop an accurate strategy for the overall rail network in Kent without considering the effect it will have on demand for domestic services.

2.    The RUS process involves Network Rail, train operating companies (Southeastern, First Capital Connect, Southern, Eurostar), Freight Operating Companies (DB Schenker, Freightliner), Department for Transport, Transport for London, Passenger Focus, local authorities and elected representatives.

3.    The document can be downloaded from:
http://www.networkrail.co.uk/browseDirectory.aspx?dir=\RUS%20Documents\Route%20Utilisation%20Strategies\Kent&pageid=4449&root=\RUS%20Documents\Route%20Utilisation%20Strategies

     
4.    The Kent RUS covers routes into London Bridge, Charing Cross Cannon Street, Victoria and Blackfriars.  It has been developed with reference to the South London RUS, which focuses specifically on improvements to the suburban network portion of the Sussex and Kent routes.  In the case of Kent, the suburban route covers the area in towards London from Bromley South, Orpington and Gravesend.

5.    The RUS strategy includes detailed recommendations covering the period up to 2020, within the context of a 30- year plan.

6.    Specific initiatives highlighted or recommended by the RUS:

- Potential benefits have been identified for extending the planned peak-only high speed service between Rochester and St Pancras to start back from Faversham.

- Extending the planned peak only high speed services between Ebbsfleet and St Pancras to start back from Ashford.  As an alternative, these services could start from Maidstone West, via Gravesend and Strood, although the benefits are fewer than extending the services to Ashford.

- Beyond 2019, the RUS supports safeguarding Crossrail extension beyond Abbey Wood to Gravesend, which could provide additional capacity to the Thames Gateway at a relatively low cost.

- New stations are recommended for further consideration, subject to the business case, at Thanet Parkway, Appledore Parkway, Wilting Farm and Maidstone Parkway (on HS1).

- Improved access to stations is supported, especially public transport connections to Ebbsfleet.

- A major re-signalling scheme, which involves replacing the signalling equipment over 50 miles between Rochester and Ramsgate and on much of the Canterbury East line will take place between 2011 and 2014.  The initiative will provide greater capacity and more flexibility, helping improve performance on the route.

7.    The high speed line between St Pancras International and the Channel Tunnel is owned by High Speed 1 and maintained under contract by Network Rail.  It was opened fully in 2007 to provide a dedicated high speed connection for Eurostar trains.  Further options exist to increase the length of the high speed trains which are currently six cars to a maximum of 12, as well as extending high speed services to start further back within Kent to meet future needs.  Not only would this add extra capacity into London, it could reduce overcrowding on traditional routes into Victoria and London Bridge.

8.    There will be trains running from Kent which connect to seven out of the 11 London terminus stations: Blackfriars, Cannon Street, Charing Cross, Kings Cross (via St Pancras), London Bridge, St Pancras International and Victoria.

Contact information

Passengers / community members
Network Rail national helpline
03457 11 41 41

Latest travel advice
Please visit National Rail Enquiries

Journalists
Network Rail press office - South East route
020 3357 7969
southeastroutecomms@networkrail.co.uk

About Network Rail

We own, operate and develop Britain's railway infrastructure; that's 20,000 miles of track, 30,000 bridges, tunnels and viaducts and the thousands of signals, level crossings and stations. We run 20 of the UK's largest stations while all the others, over 2,500, are run by the country's train operating companies.

Usually, there are almost five million journeys made in the UK and over 600 freight trains run on the network. People depend on Britain's railway for their daily commute, to visit friends and loved ones and to get them home safe every day. Our role is to deliver a safe and reliable railway, so we carefully manage and deliver thousands of projects every year that form part of the multi-billion pound Railway Upgrade Plan, to grow and expand the nation's railway network to respond to the tremendous growth and demand the railway has experienced - a doubling of passenger journeys over the past 20 years.

Follow us on Twitter: @networkrail